PRINCE2 certification · Exam PRINCE2-Practitioner

PRINCE2-Practitioner Mock Exam

PRINCE2 Practitioner Exam

Free PRINCE2-Practitioner questions on Topic 8: Progress Theme, each with the answer and an explanation.

20 questions · 33 minutes · free, no sign-up

Topic 8: Progress Theme questions

1–7 of 7 free
Question 1

Scenario:
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2. Work is to start at the beginning of week 2 (Stage 4).
3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT
equipment.
6. Installation work must take place during MFH normal working hours.
7. +£10,000 / -£25,000.
Reporting arrangements
8. Highlight Report every Monday by 10.00 am.
9. The report must contain a summary of all products worked on during the previous week.
10. Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
Column 1 is a list of actions that occur during the Controlling a Stage process. For each
action in Column 1, select from Column 2 the PRINCE2 theme that is being applied. Each
selection from Column 2 can be used once, more than once or not at all.
Drop down the answer from column 1 to column 2.

Show answerHide answer

Explanation

Question 2 Choose 1

Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company
due in part to the increased marketing activities of its competitors. To help counter this, the
company has decided to create a promotional calendar for next year for all its current and  prospective customers. The end product of this project will be a prepared calendar pack,
ready for printing. The design of the calendar will be similar to one sent out previously, and
must reflect the company image as described in the existing corporate branding standards.
Another project is currently producing a new company logo when is to be printed on each
page of the promotional calendar. The prepared calendar pack will consist of:
Design for each month - correctly showing at public holidays and new company
logo
Selected photographs- 12 professionally-produced photographs, showing different
members of staff
Selected paper and selected envelope - for printing and mailing the calendar
Chosen label design - a competition to design a label will be held as part of this
project
List of customers - names and addresses of customers to whom the calendar will
be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
Create the customer fast using information from the Accounts and Marketing
departments
Confirm compliance with the Data Protection Legislation
Create a design for each month - this will be done by the internal creative team
Select and appoint a professional photographer
Gather photograph design ideas from previous project and agree photographic
session schedule
Prepare a production cost forecast
Select paper and envelope.
Stage 3 will include the activities to:
Produce and select tie professionally-taken photographs
Hold the label design competition and choose the label design
Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing
and marketing of the calendar is to be produced in stage 2. However, the actual production
and distribution of the calendars is not within the scope of the project. The product cost
forecast will be reviewed by the Project Board to determine whether tie project should
continue.
It is now 05 October and the prepared calendar pack must be delivered to the print
company by 30 November, to enable printing and distribution of the calendar in time for
Christmas. The cost of the activities to develop the specialist products and the cost of the
project management activities are estimated to be £20,000. There is a project time
tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change
budget of £500 has been allocated but there is no risk budget.
The team member collating the list of customers has now forecast that it will NOT be
complete by the end of this stage as originally planned, due to a number of new
prospective customers' details not yet being available. What action should the team
member take?

Show answerHide answer

Correct answer: D

Raise an issue to inform the Project Manager.

Question 3 Choose 1

Which statement is TRUE with regard to technical stages?

Show answerHide answer

Correct answer: C

Technical stages often overlap

Question 4 Choose 1

Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company
due in part to the increased marketing activities of its competitors. To help counter this, the
company has decided to create a promotional calendar for next year for all its current and
prospective customers. The end product of this project will be a prepared calendar pack,
ready for printing. The design of the calendar will be similar to one sent out previously, and
must reflect the company image as described in the existing corporate branding standards.
Another project is currently producing a new company logo when is to be printed on each
page of the promotional calendar. The prepared calendar pack will consist of:
Design for each month - correctly showing at public holidays and new company
logo
Selected photographs- 12 professionally-produced photographs, showing different
members of staff
Selected paper and selected envelope - for printing and mailing the calendar
Chosen label design - a competition to design a label will be held as part of this
project
List of customers - names and addresses of customers to whom the calendar will
be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
Create the customer fast using information from the Accounts and Marketing
departments
Confirm compliance with the Data Protection Legislation
Create a design for each month - this will be done by the internal creative team
Select and appoint a professional photographer
Gather photograph design ideas from previous project and agree photographic
session schedule
Prepare a production cost forecast
Select paper and envelope.
Stage 3 will include the activities to:
Produce and select tie professionally-taken photographs
Hold the label design competition and choose the label design
Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing
and marketing of the calendar is to be produced in stage 2. However, the actual production
and distribution of the calendars is not within the scope of the project. The product cost
forecast will be reviewed by the Project Board to determine whether tie project should
continue.
It is now 05 October and the prepared calendar pack must be delivered to the print
company by 30 November, to enable printing and distribution of the calendar in time for
Christmas. The cost of the activities to develop the specialist products and the cost of the
project management activities are estimated to be £20,000. There is a project time
tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change
budget of £500 has been allocated but there is no risk budget.
During stage 2, an early review of the photo design ideas from the Marketing department
has highlighted the need for engineering machinery to be operating in the background
during the photo sessions. This requires a change to the baselined Product Description for
the photos. What action should the Project Manager take?

Show answerHide answer

Correct answer: A

Log the change in the Issue Register as a request for change.

Question 5 Choose 1

Which of the following is not a factor to consider when determining the length of a stage?

Show answerHide answer

Correct answer: A

The amount of resources available h the short term

Question 6 Choose 1

Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company
due in part to the increased marketing activities of its competitors. To help counter this, the
company has decided to create a promotional calendar for next year for all its current and
prospective customers. The end product of this project will be a prepared calendar pack,
ready for printing. The design of the calendar will be similar to one sent out previously, and
must reflect the company image as described in the existing corporate branding standards.
Another project is currently producing a new company logo when is to be printed on each
page of the promotional calendar. The prepared calendar pack will consist of:
Design for each month - correctly showing at public holidays and new company
logo
Selected photographs- 12 professionally-produced photographs, showing different
members of staff
Selected paper and selected envelope - for printing and mailing the calendar
Chosen label design - a competition to design a label will be held as part of this
project
List of customers - names and addresses of customers to whom the calendar will
be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
Create the customer fast using information from the Accounts and Marketing
departments
Confirm compliance with the Data Protection Legislation
Create a design for each month - this will be done by the internal creative team
Select and appoint a professional photographer
Gather photograph design ideas from previous project and agree photographic
session schedule
Prepare a production cost forecast
Select paper and envelope.
Stage 3 will include the activities to:
Produce and select tie professionally-taken photographs
Hold the label design competition and choose the label design
Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing
and marketing of the calendar is to be produced in stage 2. However, the actual production
and distribution of the calendars is not within the scope of the project. The product cost
forecast will be reviewed by the Project Board to determine whether tie project should
continue.
It is now 05 October and the prepared calendar pack must be delivered to the print
company by 30 November, to enable printing and distribution of the calendar in time for
Christmas. The cost of the activities to develop the specialist products and the cost of the
project management activities are estimated to be £20,000. There is a project time
tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change
budget of £500 has been allocated but there is no risk budget.
Whilst identifying the mailing costs for the calendars the Project Manager was surprised to
find the costs could vary considerably depending on the size of the package and the
delivery service used. For the purpose of this project, the Project Manager has selected an
appropriate service but feels that a corporate standard for postage would have reduced the
time and effort invested. It could reduce the company's overheads by up to £20k per year.
How should the Project Manager record this observation within the project?

Show answerHide answer

Correct answer: D

Make an entry in the Lessons Log for future consideration by corporate management.

Question 7

Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company
due in part to the increased marketing activities of its competitors. To help counter this, the
company has decided to create a promotional calendar for next year for all its current and
prospective customers. The end product of this project will be a prepared calendar pack,
ready for printing. The design of the calendar will be similar to one sent out previously, and
must reflect the company image as described in the existing corporate branding standards.
Another project is currently producing a new company logo when is to be printed on each
page of the promotional calendar. The prepared calendar pack will consist of:
Design for each month - correctly showing at public holidays and new company
logo
Selected photographs- 12 professionally-produced photographs, showing different
members of staff
Selected paper and selected envelope - for printing and mailing the calendar
Chosen label design - a competition to design a label will be held as part of this
project
List of customers - names and addresses of customers to whom the calendar will
be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
Create the customer fast using information from the Accounts and Marketing
departments
Confirm compliance with the Data Protection Legislation
Create a design for each month - this will be done by the internal creative team
Select and appoint a professional photographer
Gather photograph design ideas from previous project and agree photographic
session schedule
Prepare a production cost forecast
Select paper and envelope.
Stage 3 will include the activities to:
Produce and select tie professionally-taken photographs
Hold the label design competition and choose the label design
Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing
and marketing of the calendar is to be produced in stage 2. However, the actual production
and distribution of the calendars is not within the scope of the project. The product cost
forecast will be reviewed by the Project Board to determine whether tie project should
continue.
It is now 05 October and the prepared calendar pack must be delivered to the print
company by 30 November, to enable printing and distribution of the calendar in time for
Christmas. The cost of the activities to develop the specialist products and the cost of the
project management activities are estimated to be £20,000. There is a project time
tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change
budget of £500 has been allocated but there is no risk budget.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement
For each line identify the appropriate option, from options 1 to 6, that applies. Each option
can be used once, more than once or not at all.

Show answerHide answer

Explanation

That's the last free question in Topic 8: Progress Theme

You've seen the free 30% (7 of 24 questions). Full access unlocks every question and full-length PRINCE2-Practitioner mock exams (65 questions, 105 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the PRINCE2-Practitioner exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PRINCE2-Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PRINCE2-Practitioner mock exam
  • 65questions per mock
  • 105 mintime limit
  • 274questions in the bank
  • Newmock on every attempt