PRINCE2 certification · Exam PRINCE2-Practitioner

PRINCE2-Practitioner Mock Exam

PRINCE2 Practitioner Exam

Free PRINCE2-Practitioner questions on Topic 4: Quality Theme, each with the answer and an explanation.

20 questions · 33 minutes · free, no sign-up

Topic 4: Quality Theme questions

1–8 of 8 free
Question 1 Choose 1

Additional Information
Product Description 

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any
changes to the outsourced staff employment contracts adhere to employment law. The DIT
will review future job descriptions of the transferred staff before the final contract is signed
with the selected service provider.
The service level agreement between MFH and the selected service provider will specify
the type and quality of service required. The selected service provider must follow the
industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for
all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels
during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality
Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status,
version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to
employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of
team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by
the selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the transferred staff?

Show answerHide answer

Correct answer: C

All legal requirements are adhered to for the transfer of staff.

Question 2 Choose 1

Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any
changes to the outsourced staff employment contracts adhere to employment law. The DIT
will review future job descriptions of the transferred staff before the final contract is signed
with the selected service provider.
The service level agreement between MFH and the selected service provider will specify
the type and quality of service required. The selected service provider must follow the
industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for
all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels
during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality
Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status,
version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to
employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of
team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by
the selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the transferred facilities computer
system?

Show answerHide answer

Correct answer: C

No (zero) loss of system functionality.

Question 3 Choose 1

Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any
changes to the outsourced staff employment contracts adhere to employment law. The DIT
will review future job descriptions of the transferred staff before the final contract is signed
with the selected service provider.
The service level agreement between MFH and the selected service provider will specify
the type and quality of service required. The selected service provider must follow the
industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for
all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels
during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality
Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status,
version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to
employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of
team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by
the selected service provider to ensure that they can be achieved.
Although it is not specified in the current corporate branding standards, the MFH corporate
logo should be shown on the front page of the service level agreement.

Show answerHide answer

Correct answer: C

Raise an issue (request for change).

Question 4 Choose 2

Extract from the Project Product Description (with errors) 
Which 2 statements apply to the Development skills required section?

Show answerHide answer

Correct answer: D, E

Delete entry 15 because this skill is NOT required within this project

Add 'Knowledge of Data Protection Act.

Question 5

Extract from the Project Product Description (with errors)


Show answerHide answer

Explanation

Question 6 Choose 1

Which of the following statements would NOT be included in the Project Product
Description?

Show answerHide answer

Correct answer: D

Quality criteria

Question 7 Choose 2

Extract from the Project Product Description (with errors) 

Which 2 statements apply to the Composition section?

Show answerHide answer

Correct answer: A, B

Amend entry 2 to 'Selected paper'.

Delete entry 3 because this is NOT a major product to be delivered by this project.

Question 8 Choose 1

Which principle is central to the quality theme and provides explicit understanding of what
the project will create?

Show answerHide answer

Correct answer: B

Focus on products

That's the last free question in Topic 4: Quality Theme

You've seen the free 30% (8 of 29 questions). Full access unlocks every question and full-length PRINCE2-Practitioner mock exams (65 questions, 105 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the PRINCE2-Practitioner exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PRINCE2-Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PRINCE2-Practitioner mock exam
  • 65questions per mock
  • 105 mintime limit
  • 274questions in the bank
  • Newmock on every attempt