Which principle is supported by the activity Evaluate the Project?
Show answerHide answer
Correct answer: C
Learn from experience
PRINCE2 Practitioner Exam
Free PRINCE2-Practitioner questions on Topic 11: Managing a Stage Boundary and Closing a Project, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Which principle is supported by the activity Evaluate the Project?
Correct answer: C
Learn from experience
It is now late October and the project is in stage 3. The label design competition has been
held and the photos of the staff have been taken. The CEO and Marketing Director still
need to choose the winning label design and the 12 photos for the calendar. However, the
Executive has learned that two competitors are issuing calendars to MNO's customers by
the middle of November. After analyzing the impact of this Issue, one of the options the
Project Manager has presented to the Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if
the project Y-e to be closed now.
Which product should register that the risk of a competitor producing a calendar at the
same time was identified at the beginning of the project but the assessment of this risk
appears to have been poor?
Correct answer: C
Lessons Report
It is now late October and the project is in stage 3. The label design competition has been
held and the photos of the staff have been taken. The CEO and Marketing Director still
need to choose the winning label design and the 12 photos for the calendar. However, the
Executive has learned that two competitors are issuing calendars to MNO's customers by
the middle of November. After analyzing the impact of this Issue, one of the options the
Project Manager has presented to the Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if
the project Y-e to be closed now.
Which product should show that the photos could be used for other promotional material for
the company?
Correct answer: D
End Project Report
You've seen the free 30% (3 of 12 questions). Full access unlocks every question and full-length PRINCE2-Practitioner mock exams (65 questions, 105 minutes), a different mock on every attempt.
Full-length mocks with the same number of questions and the same time limit as the real PRINCE2-Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full PRINCE2-Practitioner mock exam