Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing
pressure to cut costs, better manage suppliers’ performance and reduce the confusion
caused by inadequate internal controls, outdated standards and outdated technology.
External consultants were employed to conduct a feasibility study to identify options to
address the problems, and the likely costs and benefits. The following options were
considered:
Do nothing.
Re-engineer selected business functions.
Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information
Technology
Division and the Facilities Division (maintenance of buildings and grounds). The
recommendations were:
One service provider should be contracted to provide the services currently provided by
the
Information Technology Division and the Facilities Division.
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes,
systems and
operating models, plus an outline Business Case for the required project. The external
consultants
also made the following recommendations for the management of the project:
Use PRINCE2.
Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating
models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to
complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the
recommendations as a basis for the project. There is an expected saving of £20m over 10
years.
The Outsourcing project has completed the Starting up a Project process and is now in the
initiation stage. Because of the strategic importance of the project, the MFH Chief
Executive Officer has taken the role of Executive. A PRINCE2-experienced Project
Manager has been appointed from within MFH. Staff within the business functions being
outsourced will work with the external consultants who conducted the feasibility study to
define the detailed designs.
Which 2 statements should be recorded under the Expected benefits heading?
Show answerHide answer
Correct answer: C, D
The total expected savings over 10 years, at current prices, is £20m. The 10-year outsourcing contract will enable MFH to stabilize costs at agreed levels.
Explanation
http://www.whatisprince2.net/prince2-theme-business-case.php