Question 21 Choose 2

Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing
pressure to cut costs, better manage suppliers’ performance and reduce the confusion
caused by inadequate internal controls, outdated standards and outdated technology.
External consultants were employed to conduct a feasibility study to identify options to
address the problems, and the likely costs and benefits. The following options were
considered:
Do nothing.
Re-engineer selected business functions.
Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information
Technology
Division and the Facilities Division (maintenance of buildings and grounds). The
recommendations were:
One service provider should be contracted to provide the services currently provided by
the
Information Technology Division and the Facilities Division.
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes,
systems and
operating models, plus an outline Business Case for the required project. The external
consultants
also made the following recommendations for the management of the project:
Use PRINCE2.
Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating
models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to
complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the
recommendations as a basis for the project. There is an expected saving of £20m over 10
years.
The Outsourcing project has completed the Starting up a Project process and is now in the
initiation stage. Because of the strategic importance of the project, the MFH Chief
Executive Officer has taken the role of Executive. A PRINCE2-experienced Project
Manager has been appointed from within MFH. Staff within the business functions being
outsourced will work with the external consultants who conducted the feasibility study to
define the detailed designs.
Which 2 statements should be recorded under the Expected benefits heading?

Show answerHide answer

Correct answer: C, D

The total expected savings over 10 years, at current prices, is £20m.

The 10-year outsourcing contract will enable MFH to stabilize costs at agreed levels.

Explanation

http://www.whatisprince2.net/prince2-theme-business-case.php

Question 22 Choose 2

Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job
very well. He injured his leg two years ago which has restricted his visits to the engineering
area. As CEO he has an overall perspective of the business strategic requirements and the
authority to commit resources as required.
Marketing Director: She has been with the company for three years, following a
successful career with a publicity company. She has the ability to represent the needs of
the business, particularly as this is a marketing project. She has the authority to commit the
annual business marketing budget, from which the project will be funded, as she sees
appropriate. She will be responsible for monitoring the expected benefits of the calendar, in
particular the improvement of the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the
company and is still as keen and energetic as the day he started. VVhilst he will not be part
of the project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document
control. They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and
office equipment needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent
photographers and a history of successful work. This company has been selected to take
the photos for the company calendar. It has yet be decided which of the photographers to
use.
Which 2 statements explain why the CEO should be appointed as the Executive for this
project?

Show answerHide answer

Correct answer: D, E

He has the authority to commit resources as required.

He has an overall perspective of the business's strategic requirements.

Question 23 Choose 2

Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job
very well. He injured his leg two years ago which has restricted his visits to the engineering
area. As CEO he has an overall perspective of the business strategic requirements and the
authority to commit resources as required.
Marketing Director: She has been with the company for three years, following a
successful career with a publicity company. She has the ability to represent the needs of
the business, particularly as this is a marketing project. She has the authority to commit the
annual business marketing budget, from which the project will be funded, as she sees
appropriate. She will be responsible for monitoring the expected benefits of the calendar, in
particular the improvement of the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the
company and is still as keen and energetic as the day he started. VVhilst he will not be part
of the project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document
control. They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and
office equipment needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent
photographers and a history of successful work. This company has been selected to take
the photos for the company calendar. It has yet be decided which of the photographers to
use. Which 2 statements explain why the Sales Manager should be appointed as User
Assurance for this project?

Show answerHide answer

Correct answer: B, C

He can provide an evaluation of the potential impact the calendar will have on sales.

He is able to advise on suitable stakeholder engagement of current and prospective
customers.

Question 24 Choose 2

Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job
very well. He injured his leg two years ago which has restricted his visits to the engineering
area. As CEO he has an overall perspective of the business strategic requirements and the
authority to commit resources as required.
Marketing Director: She has been with the company for three years, following a
successful career with a publicity company. She has the ability to represent the needs of
the business, particularly as this is a marketing project. She has the authority to commit the
annual business marketing budget, from which the project will be funded, as she sees
appropriate. She will be responsible for monitoring the expected benefits of the calendar, in
particular the improvement of the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the
company and is still as keen and energetic as the day he started. VVhilst he will not be part
of the project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document
control. They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and
office equipment needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent
photographers and a history of successful work. This company has been selected to take
the photos for the company calendar. It has yet be decided which of the photographers to
use.Which 2 statements explain why Central Records should be appointed as Project Support
for this project?

Show answerHide answer

Correct answer: A, E

They control the receipt, identification, versions, storage and issue of all project products
within the company's projects.

They have knowledge of the organizational standards that will be applicable to the
project.

Question 25 Choose 2

Additional Information

Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that
provides specialist outsourcing resources. Outcome provided the consultants who carried
out the feasibility study and the same consultants will be providing support and guidance to
the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology
Division 12 months ago. She is responsible for ensuring a cost-conscious approach is
adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides
computer hardware to all business functions but has little awareness of the needs of his
colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced andefficient qualified accountant who has much of the responsibility of running the Finance
Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's
business strategy and assisting in a full business risk assessment. He also drafted the
corporate Business Case standards.
Which 2 alternative actions apply to the proposed business assurance for this project?

Show answerHide answer

Correct answer: D, E

Add 'Director of Finance Division' because she is responsible for checking that any
supplier and contractor payments are authorized.

Retain because he is familiar with the Ministry of Food Hygiene business strategy, the
business level risk assessment and the Business Case standards.

Question 26 Choose 1

Which of the following represents the four key characteristics a good Project board should
display?

Show answerHide answer

Correct answer: B

Authority, Credibility, Delegation, Availability

Question 27 Choose 1

In which Management product would the Project Board specify where the authority for
change requests lies?

Show answerHide answer

Correct answer: D

Configuration Management Strategy

Question 28 Choose 1

Which of the following statements is true of the business interest on the project?

Show answerHide answer

Correct answer: A

Ensures the project provides value for money

Question 29 Choose 2

Additional Information

Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that
provides specialist outsourcing resources. Outcome provided the consultants who carried
out the feasibility study and the same consultants will be providing support and guidance to
the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology
Division 12 months ago. She is responsible for ensuring a cost-conscious approach is
adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides
computer hardware to all business functions but has little awareness of the needs of his
colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and
efficient qualified accountant who has much of the responsibility of running the Finance
Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's
business strategy and assisting in a full business risk assessment. He also drafted the
corporate Business Case standards.
Which 2 alternative actions apply to the proposed Senior Supplier for this project?

Show answerHide answer

Correct answer: A, B

Retain because she is responsible for the design of the future Information Technology
organization and working practices.

Add 'Director of Facilities' because he is responsible for the design of the future
organization, processes, systems and operation models for Facilities.

Question 30 Choose 1

Additional Information
Product Description 

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any
changes to the outsourced staff employment contracts adhere to employment law. The DIT
will review future job descriptions of the transferred staff before the final contract is signed
with the selected service provider.
The service level agreement between MFH and the selected service provider will specify
the type and quality of service required. The selected service provider must follow the
industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for
all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels
during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality
Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status,
version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to
employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of
team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by
the selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the transferred staff?

Show answerHide answer

Correct answer: C

All legal requirements are adhered to for the transfer of staff.

Full mock exam

Sit the PRINCE2-Practitioner exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PRINCE2-Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PRINCE2-Practitioner mock exam
  • 65questions per mock
  • 105 mintime limit
  • 274questions in the bank
  • Newmock on every attempt