PRINCE2 certification · Exam PRINCE2-Practitioner

PRINCE2-Practitioner Mock Exam

PRINCE2 Practitioner Exam

Free PRINCE2-Practitioner questions on Topic 6: Risk Theme, each with the answer and an explanation.

20 questions · 33 minutes · free, no sign-up

Topic 6: Risk Theme questions

1–4 of 4 free
Question 1 Choose 2

Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the
role of Team Manager after taking some time to understand the requirements of the
project. A contract for their services has been set up and is being monitored by the
Purchasing Manager and a Work Package has been agreed. This contract specifies that
the photographer must arrange a meeting with the Engineering Manager to establish a
schedule for the photo sessions to minimize the impact on the Engineering staff. This
meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he
reported that he has received no communication from the photographer. The Project
Manager has tried to call the photographer and has had no response. The Project Manager
believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients'
work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected
benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a
competitor also producing a calendar to be delivered earlier than the target date for this
project. There is a threat that the early release of a competitor's calendar may weaken the
impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated
benefits of the Calendar project.
Which 2 statements should be recorded under the Roles and responsibilities heading?

Show answerHide answer

Correct answer: B, D

Risks exceeding the agreed project risk tolerance will be reported to the Project Board.

Project Assurance will ensure that project risks are identified, assessed and controlled
according to the agreed risk management procedure.

Question 2 Choose 2

Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the
role of Team Manager after taking some time to understand the requirements of the
project. A contract for their services has been set up and is being monitored by the
Purchasing Manager and a Work Package has been agreed. This contract specifies that
the photographer must arrange a meeting with the Engineering Manager to establish a
schedule for the photo sessions to minimize the impact on the Engineering staff. This
meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he
reported that he has received no communication from the photographer. The Project
Manager has tried to call the photographer and has had no response. The Project Manager
believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients'
work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected
benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a
competitor also producing a calendar to be delivered earlier than the target date for this
project. There is a threat that the early release of a competitor's calendar may weaken the
impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated
benefits of the Calendar project.
Which 2 statements should be recorded under the Proximity heading?

Show answerHide answer

Correct answer: C, D

Imminent risks are those which may occur within two weeks.

Any risk with a proximity category of imminent will be estimated as having a very high
impact.

Question 3 Choose 2

Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the
role of Team Manager after taking some time to understand the requirements of the
project. A contract for their services has been set up and is being monitored by the
Purchasing Manager and a Work Package has been agreed. This contract specifies that
the photographer must arrange a meeting with the Engineering Manager to establish a
schedule for the photo sessions to minimize the impact on the Engineering staff. This
meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he
reported that he has received no communication from the photographer. The Project
Manager has tried to call the photographer and has had no response. The Project Manager
believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients'
work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected
benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a
competitor also producing a calendar to be delivered earlier than the target date for this
project. There is a threat that the early release of a competitor's calendar may weaken the
impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated
benefits of the Calendar project. Which 2 statements should be recorded under the Timing of risk management activities heading?

Show answerHide answer

Correct answer: B, E

The Project Board should hold monthly meetings to review project progress.

When authorizing a stage, the Project Board will check that the exposure to risk is still
acceptable.

Question 4 Choose 1

Which of the following statements is False regarding the Risk Management Strategy?

Show answerHide answer

Correct answer: A

It captures and maintains all relevant information on identified threats and opportunities

That's the last free question in Topic 6: Risk Theme

You've seen the free 30% (4 of 16 questions). Full access unlocks every question and full-length PRINCE2-Practitioner mock exams (65 questions, 105 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the PRINCE2-Practitioner exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PRINCE2-Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PRINCE2-Practitioner mock exam
  • 65questions per mock
  • 105 mintime limit
  • 274questions in the bank
  • Newmock on every attempt