Question 31 Choose 1

Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any
changes to the outsourced staff employment contracts adhere to employment law. The DIT
will review future job descriptions of the transferred staff before the final contract is signed
with the selected service provider.
The service level agreement between MFH and the selected service provider will specify
the type and quality of service required. The selected service provider must follow the
industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for
all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels
during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality
Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status,
version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to
employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of
team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by
the selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the transferred facilities computer
system?

Show answerHide answer

Correct answer: C

No (zero) loss of system functionality.

Question 32 Choose 1

Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any
changes to the outsourced staff employment contracts adhere to employment law. The DIT
will review future job descriptions of the transferred staff before the final contract is signed
with the selected service provider.
The service level agreement between MFH and the selected service provider will specify
the type and quality of service required. The selected service provider must follow the
industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for
all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels
during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality
Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status,
version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to
employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of
team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by
the selected service provider to ensure that they can be achieved.
Although it is not specified in the current corporate branding standards, the MFH corporate
logo should be shown on the front page of the service level agreement.

Show answerHide answer

Correct answer: C

Raise an issue (request for change).

Question 33 Choose 2

Extract from the Project Product Description (with errors) 
Which 2 statements apply to the Development skills required section?

Show answerHide answer

Correct answer: D, E

Delete entry 15 because this skill is NOT required within this project

Add 'Knowledge of Data Protection Act.

Question 34

Extract from the Project Product Description (with errors)


Show answerHide answer

Explanation

Question 35 Choose 1

Which of the following statements would NOT be included in the Project Product
Description?

Show answerHide answer

Correct answer: D

Quality criteria

Question 36 Choose 2

Extract from the Project Product Description (with errors) 

Which 2 statements apply to the Composition section?

Show answerHide answer

Correct answer: A, B

Amend entry 2 to 'Selected paper'.

Delete entry 3 because this is NOT a major product to be delivered by this project.

Question 37 Choose 1

Which principle is central to the quality theme and provides explicit understanding of what
the project will create?

Show answerHide answer

Correct answer: B

Focus on products

Question 38 Choose 1

PRINCE2 proposes 3 levels of Plan, which are they?

Show answerHide answer

Correct answer: D

Project, Stage and Team Plans

Question 39 Choose 1

Who is responsible for committing user resources to the project?

Show answerHide answer

Correct answer: A

Senior User

Question 40 Choose 2

Product Summary
A list of customers will be collated. This will use existing information from the Accounts
department about current customers, and existing information from the Marketing
department about prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast
will be produced to allow the CEO and the Marketing Director to decide whether to continue
with the project. If they decide to continue, they will give the approval to launch the internal
label design competition. Competition rules will be required to communicate details of the
competition to the staff. The chosen label design will then be selected from the competition
entries.
The photos for the calendar must be based on existing photo design ideas available from
the Marketing department. The selected photos will be chosen from these. Monthly
calendar displays will be created to show the required layout of each page.
Product Breakdown Structure (contains errors)

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as
additional intonation for this question in the Scenario Booklet, answer the following 5
questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst
photographs are being taken of the engineering staff performing their everyday duties and
operating machinery. Two weeks ago the professional photographer produced the photo
session schedule based on the operational staff schedule. The operational staff schedule is
produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the Budgets section?

Show answerHide answer

Correct answer: A, D

Amend entry 15 because it should also include the cost of management activities.

Add 'Change budget - £500'.

Full mock exam

Sit the PRINCE2-Practitioner exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PRINCE2-Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PRINCE2-Practitioner mock exam
  • 65questions per mock
  • 105 mintime limit
  • 274questions in the bank
  • Newmock on every attempt