Additional Information
Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any
changes to the outsourced staff employment contracts adhere to employment law. The DIT
will review future job descriptions of the transferred staff before the final contract is signed
with the selected service provider.
The service level agreement between MFH and the selected service provider will specify
the type and quality of service required. The selected service provider must follow the
industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for
all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels
during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality
Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status,
version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to
employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of
team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by
the selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the transferred facilities computer
system?
Show answerHide answer
Correct answer: C
No (zero) loss of system functionality.