The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost
and Quality are three of them, what are the other three?
Show answerHide answer
Correct answer: A
Scope, People & Resources, Benefit
PRINCE2 Practitioner Exam
Free PRINCE2-Practitioner questions on Topic 1: PRINCE2 Principles, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost
and Quality are three of them, what are the other three?
Correct answer: A
Scope, People & Resources, Benefit
Which of the following statements is FALSE regarding the Continued Business
Justification?
Correct answer: B
The justification for the project should remain valid
Which of the following principles describes this statement?" xxx defines tolerances for each
project objective to establish limits of delegated authority"
Correct answer: C
Manage by exception
Which of the following statements is NOT correct?
The Learn from Experience principle suggests that lessons should be actively sought...
Correct answer: B
When Initiating a Project
Which of the following principles uses Product Descriptions to provide clarity by defining
each product's purpose, composition, derivation, format, quality criteria and quality
method?
Correct answer: B
Focus on products
Which statement best explains the purpose of Tailor to suit the project environment?
Correct answer: D
To pick which PRINCE2 processes to apply and which to leave out
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out
more about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to
the increased marketing activities of its competitors. 10% of customers have not re-ordered
in this financial year and staff morale is poor. A number of skilled staff have left as a result
and replacement staff have not been recruited due to the reduced operation. If the project
is successful, a recruitment campaign will be required to fill the existing staff vacancies and
there may be a requirement for additional staff. Operational costs are likely to increase
because skilled staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an
average profit of £2k. The Marketing department believes that sending a promotional
calendar to our current and prospective customers would increase orders by at least 10%
with a minimum of 10 further orders from the list of prospective customers within 12 months
from the date of distribution.
The Marketing Director will be funding the project from the business marketing budget. She
believes that the effect of a good company image portrayed by a successful calendar would
last into a second year. She has forecast the same increase in orders for a second year
and predicts that the annual employee satisfaction survey will show a measurable
improvement in staff morale.
A number of alternatives were explored, including:
20% discount for all repeat customers - not cost-effective and very short term
A promotional calendar as a free Christmas gift - would target current and
prospective customers and the benefits would last into a second year
A series of television and press advertisements· was too expensive
A direct mail shot to all customers - benefit would be short term
Creation of an internet website - would not suit all customers
The calendar is seen as the favored option, as long as the company's competitors do not
increase their marketing activity. Whilst the Marketing department wants a very high
quality, glossy product, the project management team must be aware of the cost this will
incur.
Which 2 statements should be recorded under the Costs heading?
Correct answer: B, E
The project will be funded from the business marketing budget Project costs are estimated to be a total of £26.5k
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing
pressure to cut costs, better manage suppliers’ performance and reduce the confusion
caused by inadequate internal controls, outdated standards and outdated technology.
External consultants were employed to conduct a feasibility study to identify options to
address the problems, and the likely costs and benefits. The following options were
considered:
Do nothing.
Re-engineer selected business functions.
Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information
Technology
Division and the Facilities Division (maintenance of buildings and grounds). The
recommendations were:
One service provider should be contracted to provide the services currently provided by
the
Information Technology Division and the Facilities Division.
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes,
systems and
operating models, plus an outline Business Case for the required project. The external
consultants
also made the following recommendations for the management of the project:
Use PRINCE2.
Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating
models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to
complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the
recommendations as a basis for the project. There is an expected saving of £20m over 10
years.
The Outsourcing project has completed the Starting up a Project process and is now in the
initiation stage. Because of the strategic importance of the project, the MFH Chief
Executive Officer has taken the role of Executive. A PRINCE2-experienced Project
Manager has been appointed from within MFH. Staff within the business functions being
outsourced will work with the external consultants who conducted the feasibility study to
define the detailed designs.
Which 2 statements should be recorded under the Timescale heading?
Correct answer: A, B
The contract with the selected service provider will be agreed during stage 3. The expected benefits will be calculated over 10 years from completion of the project.
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing
pressure to cut costs, better manage suppliers’ performance and reduce the confusion
caused by inadequate internal controls, outdated standards and outdated technology.
External consultants were employed to conduct a feasibility study to identify options to
address the problems, and the likely costs and benefits. The following options were
considered:
Do nothing.
Re-engineer selected business functions.
Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information
Technology
Division and the Facilities Division (maintenance of buildings and grounds). The
recommendations were:
One service provider should be contracted to provide the services currently provided by
the
Information Technology Division and the Facilities Division.
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes,
systems and
operating models, plus an outline Business Case for the required project. The external
consultants
also made the following recommendations for the management of the project:
Use PRINCE2.
Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating
models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to
complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the
recommendations as a basis for the project. There is an expected saving of £20m over 10
years.
The Outsourcing project has completed the Starting up a Project process and is now in the
initiation stage. Because of the strategic importance of the project, the MFH Chief
Executive Officer has taken the role of Executive. A PRINCE2-experienced Project
Manager has been appointed from within MFH. Staff within the business functions being
outsourced will work with the external consultants who conducted the feasibility study to
define the detailed designs.
Which 2 statements should be recorded under the Business options heading?
Correct answer: C, D
Use external consultants to provide guidance on the detailed design of the outsourced Set up a PRINCE2 project to deliver the outsourced services.
services.
Reference: http://www.whatisprince2.net/prince2-theme-business-case.php
Additional Information 
Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that
provides specialist outsourcing resources. Outcome provided the consultants who carried
out the feasibility study and the same consultants will be providing support and guidance to
the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology
Division 12 months ago. She is responsible for ensuring a cost-conscious approach is
adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides
computer hardware to all business functions but has little awareness of the needs of his
colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and
efficient qualified accountant who has much of the responsibility of running the Finance
Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's
business strategy and assisting in a full business risk assessment. He also drafted the
corporate Business Case standards.
Which 2 alternative actions apply to the proposed supplier assurance for this project?
Correct answer: B, D
Retain because he will be able to advise on many of the products that will enable Add 'Outcome Account Manager' because he will advise on potential changes and their
outsourcing to happen, such as the 10-year outsourcing service contract.
impact on the integrity of the project's products.