Question 41

The project has a cost tolerance of +5% I ·5%, of which stage 2 has a tolerance of +£45k 1-
£45k.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement.
For each line identify the appropriate option, from options A to E, that applies. Each option
can be used once, more than once or not at all.

Show answerHide answer

Explanation

Question 42 Choose 2

Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the
role of Team Manager after taking some time to understand the requirements of the
project. A contract for their services has been set up and is being monitored by the
Purchasing Manager and a Work Package has been agreed. This contract specifies that
the photographer must arrange a meeting with the Engineering Manager to establish a
schedule for the photo sessions to minimize the impact on the Engineering staff. This
meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he
reported that he has received no communication from the photographer. The Project
Manager has tried to call the photographer and has had no response. The Project Manager
believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients'
work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected
benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a
competitor also producing a calendar to be delivered earlier than the target date for this
project. There is a threat that the early release of a competitor's calendar may weaken the
impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated
benefits of the Calendar project.
Which 2 statements should be recorded under the Roles and responsibilities heading?

Show answerHide answer

Correct answer: B, D

Risks exceeding the agreed project risk tolerance will be reported to the Project Board.

Project Assurance will ensure that project risks are identified, assessed and controlled
according to the agreed risk management procedure.

Question 43 Choose 2

Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the
role of Team Manager after taking some time to understand the requirements of the
project. A contract for their services has been set up and is being monitored by the
Purchasing Manager and a Work Package has been agreed. This contract specifies that
the photographer must arrange a meeting with the Engineering Manager to establish a
schedule for the photo sessions to minimize the impact on the Engineering staff. This
meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he
reported that he has received no communication from the photographer. The Project
Manager has tried to call the photographer and has had no response. The Project Manager
believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients'
work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected
benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a
competitor also producing a calendar to be delivered earlier than the target date for this
project. There is a threat that the early release of a competitor's calendar may weaken the
impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated
benefits of the Calendar project.
Which 2 statements should be recorded under the Proximity heading?

Show answerHide answer

Correct answer: C, D

Imminent risks are those which may occur within two weeks.

Any risk with a proximity category of imminent will be estimated as having a very high
impact.

Question 44 Choose 2

Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the
role of Team Manager after taking some time to understand the requirements of the
project. A contract for their services has been set up and is being monitored by the
Purchasing Manager and a Work Package has been agreed. This contract specifies that
the photographer must arrange a meeting with the Engineering Manager to establish a
schedule for the photo sessions to minimize the impact on the Engineering staff. This
meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he
reported that he has received no communication from the photographer. The Project
Manager has tried to call the photographer and has had no response. The Project Manager
believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients'
work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected
benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a
competitor also producing a calendar to be delivered earlier than the target date for this
project. There is a threat that the early release of a competitor's calendar may weaken the
impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated
benefits of the Calendar project. Which 2 statements should be recorded under the Timing of risk management activities heading?

Show answerHide answer

Correct answer: B, E

The Project Board should hold monthly meetings to review project progress.

When authorizing a stage, the Project Board will check that the exposure to risk is still
acceptable.

Question 45 Choose 1

Which of the following statements is False regarding the Risk Management Strategy?

Show answerHide answer

Correct answer: A

It captures and maintains all relevant information on identified threats and opportunities

Question 46 Choose 1

If the Project Board are too busy to authorize all change requests themselves they can
appoint?

Show answerHide answer

Correct answer: C

A Change Committee

Question 47 Choose 1

In which strategy would the change control process be recorded?

Show answerHide answer

Correct answer: B

Configuration Management Strategy

Question 48 Choose 1

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which
contains a document control process to manage all documentation requirements.
The document control process was created by the MFH Quality Manager, who now
maintains all of MFH's documents and performs an organization-wide configuration
management role. The MFH Quality Manager will administer the configuration

Show answerHide answer

Correct answer: A

Reduced savings, now £10m over 10 years.

Question 49 Choose 1

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which
contains a document control process to manage all documentation requirements.
The document control process was created by the MFH Quality Manager, who now
maintains all of MFH's documents and performs an organization-wide configuration
management role. The MFH Quality Manager will administer the configuration
management procedure for the Restructuring project since this must comply with
the MFH document control process.
What additional risk will this place on the project?

Show answerHide answer

Correct answer: A

None because risks associated with the centralization and rationalization of the Facilities
Division will be managed by another project.

Question 50

Scenario:
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2. Work is to start at the beginning of week 2 (Stage 4).
3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT
equipment.
6. Installation work must take place during MFH normal working hours.
7. +£10,000 / -£25,000.
Reporting arrangements
8. Highlight Report every Monday by 10.00 am.
9. The report must contain a summary of all products worked on during the previous week.
10. Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
Column 1 is a list of actions that occur during the Controlling a Stage process. For each
action in Column 1, select from Column 2 the PRINCE2 theme that is being applied. Each
selection from Column 2 can be used once, more than once or not at all.
Drop down the answer from column 1 to column 2.

Show answerHide answer

Explanation

Full mock exam

Sit the PRINCE2-Practitioner exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PRINCE2-Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PRINCE2-Practitioner mock exam
  • 65questions per mock
  • 105 mintime limit
  • 274questions in the bank
  • Newmock on every attempt