Question 51 Choose 1

Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company
due in part to the increased marketing activities of its competitors. To help counter this, the
company has decided to create a promotional calendar for next year for all its current and  prospective customers. The end product of this project will be a prepared calendar pack,
ready for printing. The design of the calendar will be similar to one sent out previously, and
must reflect the company image as described in the existing corporate branding standards.
Another project is currently producing a new company logo when is to be printed on each
page of the promotional calendar. The prepared calendar pack will consist of:
Design for each month - correctly showing at public holidays and new company
logo
Selected photographs- 12 professionally-produced photographs, showing different
members of staff
Selected paper and selected envelope - for printing and mailing the calendar
Chosen label design - a competition to design a label will be held as part of this
project
List of customers - names and addresses of customers to whom the calendar will
be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
Create the customer fast using information from the Accounts and Marketing
departments
Confirm compliance with the Data Protection Legislation
Create a design for each month - this will be done by the internal creative team
Select and appoint a professional photographer
Gather photograph design ideas from previous project and agree photographic
session schedule
Prepare a production cost forecast
Select paper and envelope.
Stage 3 will include the activities to:
Produce and select tie professionally-taken photographs
Hold the label design competition and choose the label design
Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing
and marketing of the calendar is to be produced in stage 2. However, the actual production
and distribution of the calendars is not within the scope of the project. The product cost
forecast will be reviewed by the Project Board to determine whether tie project should
continue.
It is now 05 October and the prepared calendar pack must be delivered to the print
company by 30 November, to enable printing and distribution of the calendar in time for
Christmas. The cost of the activities to develop the specialist products and the cost of the
project management activities are estimated to be £20,000. There is a project time
tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change
budget of £500 has been allocated but there is no risk budget.
The team member collating the list of customers has now forecast that it will NOT be
complete by the end of this stage as originally planned, due to a number of new
prospective customers' details not yet being available. What action should the team
member take?

Show answerHide answer

Correct answer: D

Raise an issue to inform the Project Manager.

Question 52 Choose 1

Which statement is TRUE with regard to technical stages?

Show answerHide answer

Correct answer: C

Technical stages often overlap

Question 53 Choose 1

Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company
due in part to the increased marketing activities of its competitors. To help counter this, the
company has decided to create a promotional calendar for next year for all its current and
prospective customers. The end product of this project will be a prepared calendar pack,
ready for printing. The design of the calendar will be similar to one sent out previously, and
must reflect the company image as described in the existing corporate branding standards.
Another project is currently producing a new company logo when is to be printed on each
page of the promotional calendar. The prepared calendar pack will consist of:
Design for each month - correctly showing at public holidays and new company
logo
Selected photographs- 12 professionally-produced photographs, showing different
members of staff
Selected paper and selected envelope - for printing and mailing the calendar
Chosen label design - a competition to design a label will be held as part of this
project
List of customers - names and addresses of customers to whom the calendar will
be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
Create the customer fast using information from the Accounts and Marketing
departments
Confirm compliance with the Data Protection Legislation
Create a design for each month - this will be done by the internal creative team
Select and appoint a professional photographer
Gather photograph design ideas from previous project and agree photographic
session schedule
Prepare a production cost forecast
Select paper and envelope.
Stage 3 will include the activities to:
Produce and select tie professionally-taken photographs
Hold the label design competition and choose the label design
Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing
and marketing of the calendar is to be produced in stage 2. However, the actual production
and distribution of the calendars is not within the scope of the project. The product cost
forecast will be reviewed by the Project Board to determine whether tie project should
continue.
It is now 05 October and the prepared calendar pack must be delivered to the print
company by 30 November, to enable printing and distribution of the calendar in time for
Christmas. The cost of the activities to develop the specialist products and the cost of the
project management activities are estimated to be £20,000. There is a project time
tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change
budget of £500 has been allocated but there is no risk budget.
During stage 2, an early review of the photo design ideas from the Marketing department
has highlighted the need for engineering machinery to be operating in the background
during the photo sessions. This requires a change to the baselined Product Description for
the photos. What action should the Project Manager take?

Show answerHide answer

Correct answer: A

Log the change in the Issue Register as a request for change.

Question 54 Choose 1

Which of the following is not a factor to consider when determining the length of a stage?

Show answerHide answer

Correct answer: A

The amount of resources available h the short term

Question 55 Choose 1

Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company
due in part to the increased marketing activities of its competitors. To help counter this, the
company has decided to create a promotional calendar for next year for all its current and
prospective customers. The end product of this project will be a prepared calendar pack,
ready for printing. The design of the calendar will be similar to one sent out previously, and
must reflect the company image as described in the existing corporate branding standards.
Another project is currently producing a new company logo when is to be printed on each
page of the promotional calendar. The prepared calendar pack will consist of:
Design for each month - correctly showing at public holidays and new company
logo
Selected photographs- 12 professionally-produced photographs, showing different
members of staff
Selected paper and selected envelope - for printing and mailing the calendar
Chosen label design - a competition to design a label will be held as part of this
project
List of customers - names and addresses of customers to whom the calendar will
be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
Create the customer fast using information from the Accounts and Marketing
departments
Confirm compliance with the Data Protection Legislation
Create a design for each month - this will be done by the internal creative team
Select and appoint a professional photographer
Gather photograph design ideas from previous project and agree photographic
session schedule
Prepare a production cost forecast
Select paper and envelope.
Stage 3 will include the activities to:
Produce and select tie professionally-taken photographs
Hold the label design competition and choose the label design
Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing
and marketing of the calendar is to be produced in stage 2. However, the actual production
and distribution of the calendars is not within the scope of the project. The product cost
forecast will be reviewed by the Project Board to determine whether tie project should
continue.
It is now 05 October and the prepared calendar pack must be delivered to the print
company by 30 November, to enable printing and distribution of the calendar in time for
Christmas. The cost of the activities to develop the specialist products and the cost of the
project management activities are estimated to be £20,000. There is a project time
tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change
budget of £500 has been allocated but there is no risk budget.
Whilst identifying the mailing costs for the calendars the Project Manager was surprised to
find the costs could vary considerably depending on the size of the package and the
delivery service used. For the purpose of this project, the Project Manager has selected an
appropriate service but feels that a corporate standard for postage would have reduced the
time and effort invested. It could reduce the company's overheads by up to £20k per year.
How should the Project Manager record this observation within the project?

Show answerHide answer

Correct answer: D

Make an entry in the Lessons Log for future consideration by corporate management.

Question 56

Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company
due in part to the increased marketing activities of its competitors. To help counter this, the
company has decided to create a promotional calendar for next year for all its current and
prospective customers. The end product of this project will be a prepared calendar pack,
ready for printing. The design of the calendar will be similar to one sent out previously, and
must reflect the company image as described in the existing corporate branding standards.
Another project is currently producing a new company logo when is to be printed on each
page of the promotional calendar. The prepared calendar pack will consist of:
Design for each month - correctly showing at public holidays and new company
logo
Selected photographs- 12 professionally-produced photographs, showing different
members of staff
Selected paper and selected envelope - for printing and mailing the calendar
Chosen label design - a competition to design a label will be held as part of this
project
List of customers - names and addresses of customers to whom the calendar will
be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
Create the customer fast using information from the Accounts and Marketing
departments
Confirm compliance with the Data Protection Legislation
Create a design for each month - this will be done by the internal creative team
Select and appoint a professional photographer
Gather photograph design ideas from previous project and agree photographic
session schedule
Prepare a production cost forecast
Select paper and envelope.
Stage 3 will include the activities to:
Produce and select tie professionally-taken photographs
Hold the label design competition and choose the label design
Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing
and marketing of the calendar is to be produced in stage 2. However, the actual production
and distribution of the calendars is not within the scope of the project. The product cost
forecast will be reviewed by the Project Board to determine whether tie project should
continue.
It is now 05 October and the prepared calendar pack must be delivered to the print
company by 30 November, to enable printing and distribution of the calendar in time for
Christmas. The cost of the activities to develop the specialist products and the cost of the
project management activities are estimated to be £20,000. There is a project time
tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change
budget of £500 has been allocated but there is no risk budget.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement
For each line identify the appropriate option, from options 1 to 6, that applies. Each option
can be used once, more than once or not at all.

Show answerHide answer

Explanation

Question 57 Choose 1

Who is responsible for the initial creation of the Configuration Item records?

Show answerHide answer

Correct answer: D

Project Support

Question 58

Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the
correct heading or be in the correct document

Using the Project Scenario, select the appropriate response to each of the following 5
questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar
project is a relatively simple project, the Project Manager combined the Starting Up a
Project process and the Initiating a Project process. No Project Brief has been produced.
Instead the Project Manager used the project mandate to produce a simple Project
Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist
and several Product Descriptions, Including the Project Product Description. Short sections
are also included for each of the strategies and the controls to be applied. The Project
Manager has elected to use the Daily Log to record all risks, issues, lessons and quality -
results.
After the initiation stage there will be two further stages during which a small number of
Work Packages will be authorized. While these are being managed, the Project Manager
will hold regular checkpoints, which will support the production of weekly Highlight Reports
to the Project Board.
This question provides a number of changes which may or may not be required to the
Extract from the Communication Management Strategy provided in the additional
information. Which statement applies to the Tools and techniques section?

Show answerHide answer

Correct answer: B

Move entry 4 to Reporting because this describes a report on the performance of the
Communication procedures used.

Question 59 Choose 1

M1ich statement is an appropriate entry for the outline Business Case heading within the
Project Brief?

Show answerHide answer

Correct answer: C

The project will run for two years and the benefits will be realized over 1a years.

Question 60 Choose 1

During stage 1 the level of performance expected from the service provider was changed.
After this change was agreed which of these products will require updating?

Show answerHide answer

Correct answer: B

Project Product Description because this contains details of the expected performance
of the project's products.

Full mock exam

Sit the PRINCE2-Practitioner exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PRINCE2-Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PRINCE2-Practitioner mock exam
  • 65questions per mock
  • 105 mintime limit
  • 274questions in the bank
  • Newmock on every attempt