Question 51 Choose 1
A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?
Show answerHide answer

Correct answer: C Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,

Question 52 Choose 1
Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?
Show answerHide answer

Correct answer: C Invest in coaching and training for all project team members.

Question 53 Choose 1
During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.

How should the team share tacit knowledge?
Show answerHide answer

Correct answer: B Have the team meet on a regular basis and share their experiences, challenges, and lessons learned.

Question 54 Choose 1
A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be enough to add business value.

With the project on a fixed budget, what should the project manager do next?
Show answerHide answer

Correct answer: B Gather all stakeholders and provide recommendations on a smaller, more feasible project scope,

Question 55 Choose 1
A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications

What should the project manager do?
Show answerHide answer

Correct answer: B Review the requirements traceability matrix with the team lead and the client to adequately resolve the issue

Question 56 Choose 1
A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.

What should the project manager do?
Show answerHide answer

Correct answer: D Keep project artifacts up-to-date and accessible to all stakeholders.

Question 57 Choose 1
A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor

What should the project manager have created to prevent this situation1?
Show answerHide answer

Correct answer: C Team charter

Question 58 Choose 1
A project manager for a technology project is informed by the cybersecurity team that there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.

What should the project manager direct the team to do?
Show answerHide answer

Correct answer: D Request a change through the change control process to manage the new cybersecurityrequirements.

Question 59 Choose 1
During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.

How should the project manager address the situation?
Show answerHide answer

Correct answer: C Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule.

Question 60 Choose 1
As a result of the first iteration review, the stakeholders' feedback indicated that they saw more technical features than business ones What should the project manager do?
Show answerHide answer

Correct answer: B Review this topic with the product owner before the next iteration planning

That's the last free question in Topic 4: Exam Pool D

You've seen the free 30% (60 of 201 questions). Full access unlocks every question and full-length PMP mock exams (180 questions, 230 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt