A project manager is managing a hybrid project that is using a contractor for a few key
deliverables. The contractor has been hired to perform an important delivery, but has not
yet confirmed that they can meet the required schedule.
What should the project manager do?
Show answerHide answer
Correct answer: CPlan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,
Question 52Choose 1
Many issues have been encountered in a project due to the low competence of the team
members. These issues might lead to poor project performance and potentially to project
termination.
What should the project manager do?
Show answerHide answer
Correct answer: CInvest in coaching and training for all project team members.
Question 53Choose 1
During project execution for an innovative product, a project team has been working hard to
meet the deadlines. However, one of the team members will be leaving in 3 weeks and will
be replaced with a new team member.
How should the team share tacit knowledge?
Show answerHide answer
Correct answer: BHave the team meet on a regular basis and share their experiences, challenges, and
lessons learned.
Question 54Choose 1
A project manager for a digital transformation project has already received the business
needs for the project. When gathering requirements, the project manager discovers that not
all of the requirements can be delivered with the available resources, but that some of the
requirements will be
enough to add business value.
With the project on a fixed budget, what should the project manager do next?
Show answerHide answer
Correct answer: BGather all stakeholders and provide recommendations on a smaller, more feasible
project scope,
Question 55Choose 1
A project manager Is leading an agile software development project with strict deadlines
The client complained that the last deployment did not meet the acceptance criteria The
development team lead is arguing that the deployment met all specifications and has
provided evidence of the client's specifications
What should the project manager do?
Show answerHide answer
Correct answer: BReview the requirements traceability matrix with the team lead and the client to
adequately resolve the issue
Question 56Choose 1
A project manager wants to make sure that similar projects in the future use the project's
performance data as a reference. However, the project manager is not sure how to
accomplish this.
What should the project manager do?
Show answerHide answer
Correct answer: DKeep project artifacts up-to-date and accessible to all stakeholders.
Question 57Choose 1
A project manager is working toward a deadline to prepare a client report. The project
manager prepared a meeting agenda but not a single meeting has gone according to plan
True, meetings always end in arguments and no action items come out of it. The project
manager is very frustrated and seeks help from the project sponsor
What should the project manager have created to prevent this situation1?
Show answerHide answer
Correct answer: CTeam charter
Question 58Choose 1
A project manager for a technology project is informed by the cybersecurity team that
there are changes in the government's cybersecurity requirements. The project manager
calls a team meeting to discuss the requirements, and the team learns that the design
changes can be made at no additional cost.
What should the project manager direct the team to do?
Show answerHide answer
Correct answer: DRequest a change through the change control process to manage the new
cybersecurityrequirements.
Question 59Choose 1
During the execution of a project, a company decides that everybody will need to take
vacation time before the end of the year. This may cause a change in the project time line.
How should the project manager address the situation?
Show answerHide answer
Correct answer: CAgree with functional management and team members on a vacation schedule that
would minimally impact the project schedule.
Question 60Choose 1
As a result of the first iteration review, the stakeholders' feedback indicated that they saw
more technical features than business ones What should the project manager do?
Show answerHide answer
Correct answer: BReview this topic with the product owner before the next iteration planning
That's the last free question in Topic 4: Exam Pool D
You've seen the free 30% (60 of 201 questions). Full access unlocks every question and full-length PMP mock exams (180 questions, 230 minutes), a different mock on every attempt.
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.