A project manager is consolidating information tor all the workstreams within a data center
and IT service transition project To ensure the project delivers value quickly the project
manager will assess a large number of consolidated project schedules
Which two actions should the project manager take with regard to schedule analysis?
(Choose two)
Show answerHide answer
Correct answer: A, EReview with subject matter experts (SMEs) to ensure they have contributed to the
schedule developmentEvaluate the schedules for interdependencies to establish the critical path
Question 42Choose 1
A new project manager is assigned to a project that will deliver a new and optimized credit
system. The project manager is allowed to use a hybrid approach which is new to the
organization to manage the project and new tools
In order to deliver the project successfully, what should the project manager focus on as
part of the plan?
Show answerHide answer
Correct answer: BExplain and communicate the new approach to the project sponsor and key
stakeholders
Question 43Choose 3
A protect manager is assigned to lead a global implementation of a cloud-based system
Team members are dispersed in five countries As time goes on. the project manager
notices that some team members have become quiet during status calls or other protect
discussions while others often call into meetings late and use time zone differences as the
reason for the delay
Which three actions should the project manager take to encourage engagement? (Choose
three)
Show answerHide answer
Correct answer: B, C, DForm a core group of team leads representing members from each country and
encourage them to collaborateAsk team members to agree on a meeting time prior to setting up virtual meetings ' Set
up a discussion board that allows team members to collaborate online at any time of the
dayEstablish virtual one-on-one's with team members to address any issues and/or
concerns privately
Question 44Choose 1
A supplier, who was tasked with providing an important component for a project, is unable
to deliver the materials due to a large-scale labor problem. What document should the
project manager use to update the details and communicate to relevant stakeholders?
Show answerHide answer
Correct answer: DIssue log
Question 45Choose 1
A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and
communicates it directly to management.
What should the project manager do?
Show answerHide answer
Correct answer: DDiscuss with the consultant to understand why the risk was escalated
Question 46Choose 1
A protect manager is working with the team lo deliver a project in a company that uses
different delivery methods. The project manager is concerned about the communication
channels currently suggested by the project management office (PMO) because some
information is taking too much time to reach the team members causing negative
consequences for delivery
How should the project manager avoid this situation in the future?
Show answerHide answer
Correct answer: DAgree with the project team on a suitable collaboration and make sure information is
shared at all times
Question 47Choose 1
During a project meeting, the project manager asks risk owners to present issues that may
affect the backlog. During their presentation, the project manager realizes that some risk
owners did not implement the already agreed-upon risk responses.
What should the project manager do to reduce exposure?
Show answerHide answer
Correct answer: DMeet privately with the risk owners and work with them to address any impediments to
the risk responses.
Question 48Choose 1
A project manager is managing an internal software development project that is on
schedule to complete in 1 month. The project should begin seeing value once the system is
online,
yet some stakeholders lack an understanding of how it will provide value to the
organization.
What should the project manager do next?
Show answerHide answer
Correct answer: CCoordinate with the stakeholders to ensure the benefits management plan is in
alignment with the goals.
Question 49Choose 1
A project manager has been assigned to an emergency project that must be completed
within the next few weeks. The project manager realizes this will have an impact on the
local community. As the work is near a school, the project manager has engaged with them
to understand their needs
How should the project manager ensure the work continues smoothly?
Show answerHide answer
Correct answer: DLiaise with the school to include nonworking project hours during school start and finish
times
Question 50Choose 1
Anew systems project requires feedback from the accounting manager at the beginning of
solution discussions and before meeting with other functional managers. The project
manager knows the accounting manager will not be available until a few days before the
deadline for the solution
document.
What should the project manager do to avoid a delay in the project?
Show answerHide answer
Correct answer: DBegin discussions with other functional managers and meet with the accounting
manager later.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.