Question 41 Choose 2
A project manager is consolidating information tor all the workstreams within a data center and IT service transition project To ensure the project delivers value quickly the project manager will assess a large number of consolidated project schedules

Which two actions should the project manager take with regard to schedule analysis? (Choose two)
Show answerHide answer

Correct answer: A, E Review with subject matter experts (SMEs) to ensure they have contributed to the schedule developmentEvaluate the schedules for interdependencies to establish the critical path

Question 42 Choose 1
A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools

In order to deliver the project successfully, what should the project manager focus on as part of the plan?
Show answerHide answer

Correct answer: B Explain and communicate the new approach to the project sponsor and key stakeholders

Question 43 Choose 3
A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay

Which three actions should the project manager take to encourage engagement? (Choose three)
Show answerHide answer

Correct answer: B, C, D Form a core group of team leads representing members from each country and encourage them to collaborateAsk team members to agree on a meeting time prior to setting up virtual meetings ' Set up a discussion board that allows team members to collaborate online at any time of the dayEstablish virtual one-on-one's with team members to address any issues and/or concerns privately

Question 44 Choose 1
A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use to update the details and communicate to relevant stakeholders?
Show answerHide answer

Correct answer: D Issue log

Question 45 Choose 1
A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.

What should the project manager do?
Show answerHide answer

Correct answer: D Discuss with the consultant to understand why the risk was escalated

Question 46 Choose 1
A protect manager is working with the team lo deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members causing negative consequences for delivery

How should the project manager avoid this situation in the future?
Show answerHide answer

Correct answer: D Agree with the project team on a suitable collaboration and make sure information is shared at all times

Question 47 Choose 1
During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.

What should the project manager do to reduce exposure?
Show answerHide answer

Correct answer: D Meet privately with the risk owners and work with them to address any impediments to the risk responses.

Question 48 Choose 1
A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online, yet some stakeholders lack an understanding of how it will provide value to the organization.

What should the project manager do next?
Show answerHide answer

Correct answer: C Coordinate with the stakeholders to ensure the benefits management plan is in alignment with the goals.

Question 49 Choose 1
A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs

How should the project manager ensure the work continues smoothly?
Show answerHide answer

Correct answer: D Liaise with the school to include nonworking project hours during school start and finish times

Question 50 Choose 1
Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution document.

What should the project manager do to avoid a delay in the project?
Show answerHide answer

Correct answer: D Begin discussions with other functional managers and meet with the accounting manager later.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt