A project manager has been assigned to handle a company’s newest product. The product
is in the conceptual stages and no one is sure about the success or marketability of the
product. Management wants to deliver the product in 3 months.
What should the project manager do next?
Show answerHide answer
Correct answer: AExplore the minimum requirements of the product and their feasibility.
Question 12Choose 1
Due to a statewide emergency, a project team for a global insurance company is being
forced to complete a project virtually, The project manager is tasked with conducting
meetings where confidential patient information will be presented.
What tool should the project manager use to conduct meetings with the project team and clients?
Show answerHide answer
Correct answer: BUse a password-enabled audio/video product,
Question 13Choose 1
An agile project team is tasked with a new project After multiple discussions with me
customer it appears that there is a lack of clarity on the requirements which resulted in
delays in the architecture and design phase
What should the team do next?
Show answerHide answer
Correct answer: CStart with the product prototype development, review with the customer, and gather
feedback
Question 14Choose 2
A company is implementing a project with team members who are located in different
countries and lime zones Performance assessments show that team performance is low
because the team doesn't have a common understanding about task distribution
What should the project manager do?
Show answerHide answer
Correct answer: B, DPerform team-building activitiesRevisit the communications management plan
Question 15Choose 1
A company initiated a departmental transformation project improving the processes for the
organization using a predictive approach, This is a critical project for the organization and,
in the middle of the project, the project manager noticed that one of the deliverables cannot
be produced due to a missing technical skill.
What should the project manager have done to avoid this?
Show answerHide answer
Correct answer: CIdentified all required skills during the planning of the project
Question 16Choose 1
A project manager is leading a project to modemize the information technology of a bank.
The project manager needs to determine how the project stakeholders should
communicate, and has discussed the various options with the project team.
What should the project manager do to communicate with the stakeholders?
Show answerHide answer
Correct answer: CUse a variety of communication methods that respect cultural, practical, and personal
preferences.
Question 17Choose 1
A major national company known for quality products has just selected a small
subcontracting firm to assist with a project. The project manager from the subcontracting
firm is meeting with the project team to ensure that the project is delivered according to the
customer's standards
in order to ensure this, what should the project manager define and document?
Show answerHide answer
Correct answer: DRequirements
Question 18Choose 1
A project team has finished participating in an iterative product increment planning session.
After the planning session, the team returns with a list of features to deliver.
How should the project manager ensure the product increments deliver the anticipated
requirements?
Show answerHide answer
Correct answer: CEnsure every user story has acceptance criteria.
Question 19Choose 1
A project team identified a low-cost software product available for purchase that would
drastically reduce the scope of development. The development manager has confirmed
that this tool would fulfill the business need.
What should the project manager do?
Show answerHide answer
Correct answer: DRecommend the option to the product owner for consideration.
Question 20Choose 1
A software development provider reports an issue that is blocking the other remaining deliverables What should the project manager do?
Show answerHide answer
Correct answer: DSchedule a meeting with the provider to collaborate on the options