A project manager has been assigned to a project where collaboration with the business is
a critical key factor. The project manager is not sure about which approach to use. A senior
project manager has been assigned to help the project manager.
What advice should the senior project manager provide?
Show answerHide answer
Correct answer: BSuggest using an agile approach since customer and team collaboration is critical for
project success.
Question 32Choose 1
In a standup meeting a team member has been providing the same update for five
consecutive days. The task which is on the critical path is now at risk tor delaying the
schedule. What should the project manager do?
Show answerHide answer
Correct answer: CAsk the team member if there is an impediment and help to remove the blockers
Question 33Choose 1
A project manager is working on the delivery of a solution that needs to be deployed to the
public quickly. The project team is experienced, the stakeholders are supporting the
delivery, and the customer is cooperating.
What strategy should the project manager use to ensure on-time delivery of the solution?
Show answerHide answer
Correct answer: AHave a high-level plan for incremental deliveries and get the customer's feedback as
early as possible.
Question 34Choose 1
In experienced project manager has never managed an agile project until now. Due to the
uncertainty of the project, the project manager is struggling with the definition of the project
scope and is taking a long time trying to define it.
What should the project manager do?
Show answerHide answer
Correct answer: CStart executing the project as the scope will be defined and redefined throughout the
project.
Question 35Choose 1
An agile team completes a deliverable that is to be certified by another expert team The
second team does not take the deliverable for many months What should the servant
leader do?
Show answerHide answer
Correct answer: AReview the process and remove the impediment
Question 36Choose 1
A project manager is evaluating a project and realizes that its earned value (EV) shows the
cost spent is higher than the value delivered. The project manager then discovers that the
team has been adding small features that are not part of the requirements.
What should the project manager do?
Show answerHide answer
Correct answer: AAsk the team to focus on and deliver only the agreed-upon features.
Question 37Choose 2
After months of careful planning and discussions with subject matter experts (SMEs). a
new law is announced that may significantly impact the project budget. What should the
project manager do first?
Show answerHide answer
Correct answer: A, DConsult the risk and issue logs.Discuss with the project sponsor.
Question 38Choose 1
we architects are unable to agree on how to approach certain components of the
development that will be included In the upcoming sprint. After a one-on-one discussion,
the architects have decided to each own a particular module of the system, and the team
supports the decision.
What should the project manager do?
Show answerHide answer
Correct answer: DSupport the outcome of the architects’ agreement.
Question 39Choose 1
A customer is meeting with an agile team at regular intervals and keeps changing priorities
for the team members. What should the project manager do to remove this impediment?
Show answerHide answer
Correct answer: BAsk the customer to discuss these changes with the product owner.
Question 40Choose 1
During the execution phase of a project, all project team members were forced to work
from their homes rather than in person During this time, the project manager discovered
that 0.-10 team member has made disrespectful remarks about another team member to
other team members.
How should the project manager handle this situation''
Show answerHide answer
Correct answer: CCoordinate a video conference with the offending team member to resolve the issue