Question 31 Choose 1
A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?
Show answerHide answer

Correct answer: B Suggest using an agile approach since customer and team collaboration is critical for project success.

Question 32 Choose 1
In a standup meeting a team member has been providing the same update for five consecutive days. The task which is on the critical path is now at risk tor delaying the schedule. What should the project manager do?
Show answerHide answer

Correct answer: C Ask the team member if there is an impediment and help to remove the blockers

Question 33 Choose 1
A project manager is working on the delivery of a solution that needs to be deployed to the public quickly. The project team is experienced, the stakeholders are supporting the delivery, and the customer is cooperating.

What strategy should the project manager use to ensure on-time delivery of the solution?
Show answerHide answer

Correct answer: A Have a high-level plan for incremental deliveries and get the customer's feedback as early as possible.

Question 34 Choose 1
In experienced project manager has never managed an agile project until now. Due to the uncertainty of the project, the project manager is struggling with the definition of the project scope and is taking a long time trying to define it.

What should the project manager do?
Show answerHide answer

Correct answer: C Start executing the project as the scope will be defined and redefined throughout the project.

Question 35 Choose 1
An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?
Show answerHide answer

Correct answer: A Review the process and remove the impediment

Question 36 Choose 1
A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements.

What should the project manager do?
Show answerHide answer

Correct answer: A Ask the team to focus on and deliver only the agreed-upon features.

Question 37 Choose 2
After months of careful planning and discussions with subject matter experts (SMEs). a new law is announced that may significantly impact the project budget. What should the project manager do first?
Show answerHide answer

Correct answer: A, D Consult the risk and issue logs.Discuss with the project sponsor.

Question 38 Choose 1
we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.

What should the project manager do?
Show answerHide answer

Correct answer: D Support the outcome of the architects’ agreement.

Question 39 Choose 1
A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?
Show answerHide answer

Correct answer: B Ask the customer to discuss these changes with the product owner.

Question 40 Choose 1
During the execution phase of a project, all project team members were forced to work from their homes rather than in person During this time, the project manager discovered that 0.-10 team member has made disrespectful remarks about another team member to other team members.

How should the project manager handle this situation''
Show answerHide answer

Correct answer: C Coordinate a video conference with the offending team member to resolve the issue

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt