Question 71 Choose 1
A project manager is using a hybrid approach for a project. The project team created and reviewed the risk tog with the stakeholders at the beginning of the project However midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies

When should the risks be reviewed to ensure alignment between the project team and the stakeholders'?
Show answerHide answer

Correct answer: D During each iteration and review

Question 72 Choose 1
Due to a recent company merger, a project manager from company B has been assigned to a team that is comprised of team members from company A. At the start of the project, conflicts arise due to a lack of clarity on processes and the project manager's relationship with company B.

What should the project manager do to resolve this conflict?
Show answerHide answer

Correct answer: D Work with the team to analyze which processes are suitable to use and define them inthe ground rules.

Question 73 Choose 1
An agile project is 25% complete when the product owner changes The new product owner does not show interest in the project s success, and one of the sprints 901 delayed as the deliverable was not approved on time

What should the project manager have done to avoid this delay?
Show answerHide answer

Correct answer: D Reevaluated the new product owner's needs for better engagement

Question 74 Choose 1
An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.

What tools should the agile project manager use to do these estimates?
Show answerHide answer

Correct answer: D Backlog grooming, product backlog, minimum viable product (MVP)

Question 75 Choose 1
The marketing team is moving from predictive to hybrid approaches for their projects. The marketing director is not familiar with hybrid approaches and does not support the new direction. What should the project manager do?
Show answerHide answer

Correct answer: C Train the marketing team and keep their director informed.

Question 76 Choose 1
A new project manager has been assigned to an environmental project. After reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.

Why is this situation problematic?
Show answerHide answer

Correct answer: C The project manager is obligated to comply with the project location's regulatoryrequirements.

That's the last free question in Topic 3: Exam Pool C

You've seen the free 30% (76 of 254 questions). Full access unlocks every question and full-length PMP mock exams (180 questions, 230 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt