A project manager is using a hybrid approach for a project. The project team created and
reviewed the risk tog with the stakeholders at the beginning of the project However midway
through the project, the project team and stakeholders became misaligned with the risks
and mitigation strategies
When should the risks be reviewed to ensure alignment between the project team and the
stakeholders'?
Show answerHide answer
Correct answer: DDuring each iteration and review
Question 72Choose 1
Due to a recent company merger, a project manager from company B has been
assigned to a team that is comprised of team members from company A. At the start of the
project, conflicts arise due to a lack of clarity on processes and the project manager's
relationship with company B.
What should the project manager do to resolve this conflict?
Show answerHide answer
Correct answer: DWork with the team to analyze which processes are suitable to use and define them
inthe ground rules.
Question 73Choose 1
An agile project is 25% complete when the product owner changes The new product owner
does not show interest in the project s success, and one of the sprints 901 delayed as the
deliverable was not approved on time
What should the project manager have done to avoid this delay?
Show answerHide answer
Correct answer: DReevaluated the new product owner's needs for better engagement
Question 74Choose 1
An agile project manager has just been given a sizeable software development project to
implement. Early in the initiation stage, the project sponsor requests an indication of time
lines for delivery of the initial release.
What tools should the agile project manager use to do these estimates?
The marketing team is moving from predictive to hybrid approaches for their projects. The
marketing director is not familiar with hybrid approaches and does not support the new
direction. What should the project manager do?
Show answerHide answer
Correct answer: CTrain the marketing team and keep their director informed.
Question 76Choose 1
A new project manager has been assigned to an environmental project. After
reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager
wants to fix this issue immediately.
Why is this situation problematic?
Show answerHide answer
Correct answer: CThe project manager is obligated to comply with the project location's
regulatoryrequirements.
That's the last free question in Topic 3: Exam Pool C
You've seen the free 30% (76 of 254 questions). Full access unlocks every question and full-length PMP mock exams (180 questions, 230 minutes), a different mock on every attempt.
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.