During the early phases of a project, mitigation actions were not executed in a
timely manner; therefore, the project schedule was impacted. Several project stakeholders
are
now frustrated with the delays.
What should the project manager have done to manage the issue?
Show answerHide answer
Correct answer: CIdentified the appropriate response and had it implemented
Question 22Choose 1
A project manager realizes that the team members are new to the hybrid approach and do
not value standup meetings. Team members often arrive late. Digress into solutioning. or
skip the meetings altogether.
How should the project manager improve this situation with the project team?
Show answerHide answer
Correct answer: AEngage the project team In implementing and Improving key aspects of the standup
meetings.
Question 23Choose 1
A project manager has recently joined a small company. The company's chief
operating officer (COO) asked the team to skip some steps in the process in order to work more quickly. The project manager wants to ensure that these steps are not skipped in the
future.
What should the project manager do?
Show answerHide answer
Correct answer: ANotify all team members that all steps in the process must be completed.
Question 24Choose 1
An international client contacted a software development company to build out a
software product, and an agile project manager was assigned. At one of the review
meetings,
the client complains that a feature mentioned at the initial debriefing was not implemented.
What should the project manager do?
Show answerHide answer
Correct answer: DTreat it as a change request and assess the effect on the project's goals.
Question 25Choose 1
A team member is always late to work. The project manager is concerned that this may
affect the motivation of other team members The project manager tells the new team
member to align with the team's principles and arrive on time
What kind of conflict resolution did the project manager apply in this situation?
Show answerHide answer
Correct answer: DForce/direct
Question 26Choose 1
An organization is producing a product using a hybrid approach with several phases. Some
of the phases are planned to be executed in predictive and some in agile. During the agile
phase, the project manager notices that the team members sometimes unknowingly work
on the same task.
What should the project manager do?
Show answerHide answer
Correct answer: ACommunicate the task assignments to the team members in a clear manner.
Question 27Choose 1
In a hybrid project, 100 new base stations are being added to a 4G mobile network
every month. At the end of the first month, the team is behind the target and the operator is
losing money. The stakeholders are requesting information on when the base stations can
go
live and begin to bill.
What should the project manager do to take the schedule back and accelerate the return
on
investment (ROI) of the project?
A project team is facing challenges understanding how to deliver a project's scope.
A senior subject matter expert (SME) from the organization's global office is in town for 1
week.
What should the project manager do to benefit from the SME's presence?
Show answerHide answer
Correct answer: CMeet with the SME to discuss the current challenges the team is facing.
Question 29Choose 1
A project manager has heard about the large volume of emails the team receives each day
which prevents them from doing project work. One team member has stated that they
would like to be able to access project-related information when needed
To what type of communication is the team member referring?
Show answerHide answer
Correct answer: CPull communication
Question 30Choose 1
During the executing phase, a project manager is reviewing the issue log and finds
there are outstanding high-priority issues that are still open. Most of the open issues
require
effort from external domain experts who are not on the project team.
What should the project manager do?
Show answerHide answer
Correct answer: BReview the open issues with the issue reporter and issue a change request to hire
anexternal domain expert.