Question 41
A retail company identifies that it is losing sales because customers are not promptly informed about promotions and sales points. The company needs to react quickly. A project charter is created along with requests to develop a mobile application for the customer. The marketing department has a long list of features to add to the application, but there are no specifications.

Considering the objective to deploy customer value, which project life cycle approach should be chosen?
Show answerHide answer

Explanation

Question 42 Choose 1
A project manager notices that the response action for an identified issue is insufficient for solving the problem What should the project manager do next?
Show answerHide answer

Correct answer: D Meet with the project team to find another solution

Question 43 Choose 1
During the planning for a long project, the project manager recognized that several members of the team are new to their roles. How should the project manager incorporate this into planning?
Show answerHide answer

Correct answer: C Assess the training requirements and ensure time for professional developmenttraining by senior members.

Question 44 Choose 1
The sponsor approaches the project manager with new features they want added to the project. The project is 95% complete, but the sponsor insists that continued support for the project relies on the addition of the new features.

What should the project manager do?
Show answerHide answer

Correct answer: A Assess the impact of the features and refer it to the change control board (CCB).

Question 45 Choose 1
A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?
Show answerHide answer

Correct answer: B Projects that maximize the business value

Question 46 Choose 1
A project sponsor has requested a trend analysis of all risks that the project has monitored over the past 12 months. What should the agile project manager do?
Show answerHide answer

Correct answer: C Extract this from the project risk register tracking tool and issues log.

Question 47 Choose 1
During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?
Show answerHide answer

Correct answer: C Facilitate sprint planning sessions with a focus on defining the minimum viable product(MVP).

Question 48 Choose 1
A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule

What should the project manager do?
Show answerHide answer

Correct answer: C Make sure all stakeholders have access to the system and know where to find project artifacts

Question 49 Choose 1
A hybrid project manager has taken over a large-scale software development project m a highly regulated environment. During a handover session the outgoing project manager explains that they devised their own status reports which is different from the project management office's (PMO's) status report style. The project stakeholders are extremely particular about the information they receive in updates and do not believe the PMO's status reports have sufficient enough information

How should the new project manager proceed*?
Show answerHide answer

Correct answer: D Meet with the project stakeholders to explain the need to comply with the PMO standards and update the status report format accordingly

Question 50 Choose 1
A protect manager is struggling to obtain participation from key stakeholders who do not usually attend project meetings What should the project manager do1?
Show answerHide answer

Correct answer: D Set clear meeting expectations by sharing agendas in advance

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt