A large company is transitioning its projects to an agile approach After the transition
executive management requests the information that was previously available in old reports
and dashboards Many of the old reports and dashboards are no longer relevant after the
shift to agile practices.
What should the project manager do in this situation?
Show answerHide answer
Correct answer: CHelp the management team understand how the change to an agile approach impacts
the relevance of certain reports and key performance indicators (KPls)
Question 52Choose 1
A company is moving to a hybrid approach and conducted capacity activities for all of the project managers. During these capacity-building activities, the focus was on agile
approaches and team facilitation skills. When starting the implementation phase, the
project managers faced issues motivating the newly hired agile staff.
Why are the project managers having issues motivating the agile staff?
Show answerHide answer
Correct answer: DProject managers are expected to become coaches in agile teams.
Question 53Choose 1
In an agile product development environment, work is distributed to Cities A, B, and
C, which are geographically dispersed. The small teams work and collaborate to deliver the
sprints.
• City A's team focuses on the features of data capture.
• City B's team focuses on the user experience and development pieces.
• City C's team coordinates testing.
What should the project manager do to ensure a successful rollout of sprints?
Show answerHide answer
Correct answer: BImplement communication techniques and ensure the teams follow a relay pattern
ofhanding off work from one team to the other.
Question 54Choose 1
A project manager is instructed by the project sponsor to draft the project charter. The
project sponsor asks the project manager to involve a particular stakeholder m order to
provide necessary resources However, the stakeholder is refusing to get involved because
the stakeholder thinks mat there is no benefit m using the project deliverable
What should the project manager do to resolve this?
Show answerHide answer
Correct answer: AMeet with the stakeholder to discuss the impact of the deliverable
Question 55Choose 1
Throughout an entire project, the project manager took notes at every meeting with
team members. These notes provided useful insights from key stakeholders, which later
resulted in increased value to the project. The project manager thought it would be helpful
to
keep these notes as a future reference for other project managers within the organization.
Where should the notes be located?
Show answerHide answer
Correct answer: BOrganizational process assets (OPAs)
Question 56Choose 1
A project manager for an iterative project received feedback from an on-site team member
that the virtual team was not meeting the deliverables on time. The project manager
gathered details on what the status report should contain m order to track deliverables
What is the remedial action the project manager should take?
Show answerHide answer
Correct answer: APerform stakeholder engagement with the virtual team
Question 57Choose 1
There is a problem with a project because some features are not in compliance with
regulations. Some stakeholders do not believe compliance is a priority, while others
disagree.
What should the project manager do?
Show answerHide answer
Correct answer: DSend out documentation to align stakeholder expectations and project objectives.
Question 58Choose 1
A project team is reviewing solved project issues from the last phase of a project. The lead
risk analyst points out that the next phase of the project includes a critical element with
some
reserves needed
What should the project manager do to successfully complete the next phase?
Show answerHide answer
Correct answer: ARequest a reserve analysis and update the risk management plan
Question 59Choose 1
An issue reoccurs six months after a project's go-live date despite being resolved
during the project life cycle. What should the project manager have done in the previous
phase to avoid this issue?
Show answerHide answer
Correct answer: BEnsured the project team applied a long-term solution for the issue
Question 60Choose 1
The Scrum team working with the quality department has been shifting away from the
Business unit due to unclear product requirements. It is now the third sprint and both teams
have been at a standstill for a few days.
What should the project leader do to solve this situation?
Show answerHide answer
Correct answer: AAnalyze the problem with both teams to figure out If pan of the work must be redone.