PMI certification · Exam PMP

PMP Mock Exam Page 6

Project Management Professional (PMP) July 2026 Update

Free PMP questions on Topic 3: Exam Pool C, each with the answer and an explanation.

20 questions · 26 minutes · free, no sign-up

Topic 3: Exam Pool C questions

51–60 of 76 free
Question 51 Choose 1
A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.

What should the project manager do in this situation?
Show answerHide answer

Correct answer: C Help the management team understand how the change to an agile approach impacts the relevance of certain reports and key performance indicators (KPls)

Question 52 Choose 1
A company is moving to a hybrid approach and conducted capacity activities for all of the project managers. During these capacity-building activities, the focus was on agile approaches and team facilitation skills. When starting the implementation phase, the project managers faced issues motivating the newly hired agile staff.

Why are the project managers having issues motivating the agile staff?
Show answerHide answer

Correct answer: D Project managers are expected to become coaches in agile teams.

Question 53 Choose 1
In an agile product development environment, work is distributed to Cities A, B, and C, which are geographically dispersed. The small teams work and collaborate to deliver the sprints.

• City A's team focuses on the features of data capture.

• City B's team focuses on the user experience and development pieces.

• City C's team coordinates testing.

What should the project manager do to ensure a successful rollout of sprints?
Show answerHide answer

Correct answer: B Implement communication techniques and ensure the teams follow a relay pattern ofhanding off work from one team to the other.

Question 54 Choose 1
A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable

What should the project manager do to resolve this?
Show answerHide answer

Correct answer: A Meet with the stakeholder to discuss the impact of the deliverable

Question 55 Choose 1
Throughout an entire project, the project manager took notes at every meeting with team members. These notes provided useful insights from key stakeholders, which later resulted in increased value to the project. The project manager thought it would be helpful to keep these notes as a future reference for other project managers within the organization.

Where should the notes be located?
Show answerHide answer

Correct answer: B Organizational process assets (OPAs)

Question 56 Choose 1
A project manager for an iterative project received feedback from an on-site team member that the virtual team was not meeting the deliverables on time. The project manager gathered details on what the status report should contain m order to track deliverables

What is the remedial action the project manager should take?
Show answerHide answer

Correct answer: A Perform stakeholder engagement with the virtual team

Question 57 Choose 1
There is a problem with a project because some features are not in compliance with regulations. Some stakeholders do not believe compliance is a priority, while others disagree.

What should the project manager do?
Show answerHide answer

Correct answer: D Send out documentation to align stakeholder expectations and project objectives.

Question 58 Choose 1
A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some reserves needed

What should the project manager do to successfully complete the next phase?
Show answerHide answer

Correct answer: A Request a reserve analysis and update the risk management plan

Question 59 Choose 1
An issue reoccurs six months after a project's go-live date despite being resolved during the project life cycle. What should the project manager have done in the previous phase to avoid this issue?
Show answerHide answer

Correct answer: B Ensured the project team applied a long-term solution for the issue

Question 60 Choose 1
The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.

What should the project leader do to solve this situation?
Show answerHide answer

Correct answer: A Analyze the problem with both teams to figure out If pan of the work must be redone.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt