Question 81 Choose 1

Activity cost estimates and the project schedule are inputs to which Project Cost Management
process?

Show answerHide answer

Correct answer: D

Determine Budget

Question 82 Choose 1

In project management, a temporary project can be:

Show answerHide answer

Correct answer: C

Long in duration

Question 83 Choose 1

Which document in the project management plan can be updated in the Plan Procurement
Management process?

Show answerHide answer

Correct answer: C

Requirements documentation

Question 84 Choose 1

Which type of probability distribution is used to represent uncertain events such as the outcome of
a test or a possible scenario in a decision tree?

Show answerHide answer

Correct answer: C

Discrete

Question 85 Choose 1

Which change request is an intentional activity that realigns the performance of the project work
with the project management plan?

Show answerHide answer

Correct answer: D

Corrective action

Question 86 Choose 1

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour,
how many hours are required to produce 12,000 units?

Show answerHide answer

Correct answer: A

100

Question 87 Choose 1

Which stakeholder approves a project's result?

Show answerHide answer

Correct answer: A

Customer

Question 88 Choose 1

Which process involves determining, documenting, and managing stakeholders' needs and
requirements to meet project objectives?

Show answerHide answer

Correct answer: A

Collect Requirements

Question 89 Choose 1

Plan Communications Management develops an approach and plan for project communications
based on stakeholders' needs and requirements and:

Show answerHide answer

Correct answer: A

Available organizational assets

Question 90 Choose 1

The stakeholder register is an output of:

Show answerHide answer

Correct answer: A

Identify Stakeholders.

Full mock exam

Sit the CAPM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CAPM mock exam
  • 65questions per mock
  • 105 mintime limit
  • 785questions in the bank
  • Newmock on every attempt