During which process does the project team receive bids and proposals?
Show answerHide answer
Correct answer: A
Conduct Procurements
Certified Associate in Project Management
Free CAPM mock exam questions 51–60, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
During which process does the project team receive bids and proposals?
Correct answer: A
Conduct Procurements
The process of monitoring the status of the project and product scope as well as managing the
changes to the scope baseline is known as:
Correct answer: C
Control Scope.
Which output is the approved version of the time-phased project budget?
Correct answer: D
Cost baseline
The purpose of the Project Communications Management Knowledge Area is to:
Correct answer: D
Ensure timely and appropriate collection of project information.
Processes in the Initiating Process Group may be completed at the organizational level and be
outside of the project's:
Correct answer: A
Level of control.
At the completion of a project, a report is prepared that details the outcome of the research
conducted on a global trend during the project. Which item did this project create?
Correct answer: A
Result
Power, urgency, and legitimacy are attributes of which stakeholder classification model?
Correct answer: A
Salience
Through whom do project managers accomplish work?
Correct answer: D
Project team members and stakeholders
Which quality tool may prove useful in understanding and estimating the cost of quality in a
process?
Correct answer: C
Flowcharts
The following is a network diagram for a project
The total float for the project is how many days?
Correct answer: B
9