Question 61 Choose 1

Retreating from an actual or potential conflict or postponing the issue to be better prepared or to
be resolved by others describes which of the five general techniques for managing conflict?

Show answerHide answer

Correct answer: B

Withdraw/avoid

Question 62 Choose 1

Specification of both the deliverables and the processes is the focus of:

Show answerHide answer

Correct answer: B

Question 63 Choose 1

Which output of Project Cost Management consists of quantitative assessments of the probable
costs required to complete project work?

Show answerHide answer

Correct answer: A

Activity cost estimates

Question 64 Choose 1

While processes in the Planning Process Group seek to collect feedback and define project
documents to guide project work, organizational procedures dictate when the project planning:

Show answerHide answer

Correct answer: A

 ends.

Question 65 Choose 1

A stakeholder expresses a need not known to the project manager. The project manager most
likely missed a step in which stakeholder management process?

Show answerHide answer

Correct answer: A

Plan Stakeholder Management

Question 66 Choose 1

Skills necessary for project management such as motivating to provide encouragement; listening
actively; persuading a team to perform an action; and summarizing, recapping, and identifying
next steps are known as:

Show answerHide answer

Correct answer: C

communication skills

Question 67 Choose 1

Which tools or techniques are used during the Close Project or Phase process?

Show answerHide answer

Correct answer: C

Expert judgment and analytical techniques

Question 68 Choose 1

When a project is undertaken to reduce defects in a product or service, the objective of the project
is to create a/an:

Show answerHide answer

Correct answer: A

improvement

Question 69 Choose 1

The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its
risk:

Show answerHide answer

Correct answer: D

appetite

Question 70 Choose 1

The zero duration of milestones in project planning occurs because milestones:

Show answerHide answer

Correct answer: C

Represent a moment in time such as a significant project point or event.

Full mock exam

Sit the CAPM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CAPM mock exam
  • 65questions per mock
  • 105 mintime limit
  • 785questions in the bank
  • Newmock on every attempt