Question 1 Choose 1

Under which circumstances should multiple projects be grouped in a program?

Show answerHide answer

Correct answer: A

When they are needed to accomplish a set of goals and objectives for an organization

Question 2 Choose 1

Which action should the project manager take after the team finishes executing the scope?

Show answerHide answer

Correct answer: A

Verify the deliverables to ensure that they are correct and meet the customer's satisfaction.

Question 3 Choose 1

How can a project manager evaluate project team development?

Show answerHide answer

Correct answer: A

Produce team performance assessments.

Question 4 Choose 1

The procurement requirements for a project include working with several vendors. What
should the project manager take into consideration during the Project Procurement
Management processes?

Show answerHide answer

Correct answer: D

Procurement management plan

Question 5 Choose 1

According to the PMI Talent Triangle. leadership skills relate to the ability to:

Show answerHide answer

Correct answer: D

guide, motivate, and direct a team to reach project goals

Question 6 Choose 1

The project manager is creating the communications management plan Which group of
inputs Is required to begin?

Show answerHide answer

Correct answer: C

Project charter, project management plan, and project documents

Question 7 Choose 1

Which tools and techniques will a project manager use to develop a project charter?

Show answerHide answer

Correct answer: D

Expert judgment, data gathering. interpersonal and team skills, and meetings

Question 8 Choose 1

When managing costs in an agile environment, what should a project manager consider?

Show answerHide answer

Correct answer: A

Lightweight estimation methods can be used as changes arise.

Question 9 Choose 1

Howls program success measured?

Show answerHide answer

Correct answer: A

By delivering the benefit of managing the program's projects in a coordinated manner

Question 10 Choose 1

Why is tailoring required in a project?

Show answerHide answer

Correct answer: C

Because tailoring allows us to identify the techniques, procedures, and system practices
used by those in the project.

Full mock exam

Sit the CAPM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CAPM mock exam
  • 65questions per mock
  • 105 mintime limit
  • 785questions in the bank
  • Newmock on every attempt