Which document defines how a project is executed, monitored and controlled, and closed?
Show answerHide answer
Correct answer: C
Project management plan
Certified Associate in Project Management
Free CAPM questions on Topic 1, Volume A, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Which document defines how a project is executed, monitored and controlled, and closed?
Correct answer: C
Project management plan
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a
typical project progresses?
Correct answer: C
Risk and uncertainty decrease; the cost of changes increases.
Which tool or technique is used in the Plan Scope Management process?
Correct answer: D
Expert judgment
Which tool or technique is an examination of industry and specific vendor capabilities?
Correct answer: B
Market research
An input used in developing the communications management plan is:
Correct answer: B
Enterprise environmental factors.
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend
analysis are examples of which tool or technique?
Correct answer: D
Analytical techniques
The Perform Quality Assurance process occurs in which Process Group?
Correct answer: A
Executing
Enterprise environmental factors are an input to which process?
Correct answer: C
Plan Scope Management
Which process develops options and actions to enhance opportunities and reduce threats to
project objectives?
Correct answer: D
Plan Risk Responses
The process of establishing the policies, procedures, and documentation for planning, developing,
managing, executing, and controlling the project schedule is known as:
Correct answer: A
Plan Schedule Management.
Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full CAPM mock exam