Projects are undertaken by an organization to support the:
Show answerHide answer
Correct answer: D
Organizational strategy
Certified Associate in Project Management
Free CAPM mock exam questions 111–120, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Projects are undertaken by an organization to support the:
Correct answer: D
Organizational strategy
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur
is very high (0.80)?
Correct answer: C
0.70
Which of the seven basic quality tools is especially useful for gathering attributes data while
performing inspections to identify defects?
Correct answer: D
Checksheets
The most commonly used type of precedence relationship in the precedence diagramming method
(PDM) is:
Correct answer: C
finish-to-start (FS)
Work performance information and cost forecasts are outputs of which Project Cost Management
process?
Correct answer: D
Control Costs
Which technique should a project manager use in a situation in which a collaborative approach to
conflict management is not possible?
Correct answer: B
Avoidance
The procurement process that documents agreements and related documentation for future
reference is known as:
Correct answer: C
Close Procurements.
The links between the processes in the Process Groups are often:
Correct answer: B
Iterative
The scope of a project cannot be defined without some basic understanding of how to create the
specified:
Correct answer: C
product
The creation of an internet site to engage stakeholders on a project is an example of which type of
communication?
Correct answer: B
Pull
Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full CAPM mock exam