PMI certification · Exam CAPM

CAPM Mock Exam Page 11

Certified Associate in Project Management

Free CAPM mock exam questions 101–110, each with the answer and an explanation.

20 questions · 33 minutes · free, no sign-up

Free CAPM questions

101–110 of 232 free
Question 101 Choose 1

The formal and informal interaction with others in an organization industry, or professional
environment is known as:

Show answerHide answer

Correct answer: D

networking

Question 102 Choose 1

Which process is included in the Project Integration Management Knowledge Area?

Show answerHide answer

Correct answer: D

Direct and Manage Project Work

Question 103 Choose 1

The process of identifying and documenting the specific actions to be performed to produce the
project deliverables is known as:

Show answerHide answer

Correct answer: A

Define Activities.

Question 104 Choose 1

Which document includes the project scope, major deliverables, assumptions, and constraints?

Show answerHide answer

Correct answer: B

Project scope statement

Question 105 Choose 1

When an activity cannot be estimated with a reasonable degree of confidence, the work within the
activity is decomposed into more detail using which type of estimating?

Show answerHide answer

Correct answer: A

Bottom-up

Question 106 Choose 1

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components
of which subsidiary plan?

Show answerHide answer

Correct answer: D

Risk management plan

Question 107 Choose 1

Project or phase closure guidelines or requirements, historical information, and the lessons
learned knowledge base are examples of which input to the Close Project or Phase process?

Show answerHide answer

Correct answer: A

Organizational process assets

Question 108 Choose 1

The project manager notes that stakeholders are aware of the project and potential impacts and
are actively engaged in ensuring that the project is a success. The engagement level of the
stakeholders should be classified as:

Show answerHide answer

Correct answer: B

Leading

Question 109 Choose 1

Which of the following is a narrative description of products, services, or results to be delivered by
a project?

Show answerHide answer

Correct answer: A

Project statement of work

Question 110 Choose 1

A project manager seeking insight on previous stakeholder management plans and their
effectiveness should evaluate:

Show answerHide answer

Correct answer: A

Historical information and the lessons-learned database.

Full mock exam

Sit the CAPM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CAPM mock exam
  • 65questions per mock
  • 105 mintime limit
  • 785questions in the bank
  • Newmock on every attempt