Fast tracking is a schedule compression technique used to shorten the project schedule without
changing project scope. Which of the following can result from fast tracking?

Show answerHide answer

Correct answer: A

The risk of achieving the shortened project time is increased.

Question 2 Choose 1

Requirements documentation, requirements management plan, and requirements traceability
matrix are all outputs of which process?

Show answerHide answer

Correct answer: B

Collect Requirements

Question 3 Choose 1

Which of the following is a strategy to deal with positive risks or opportunities?

Show answerHide answer

Correct answer: C

Exploit

Question 4 Choose 1

What are the identified risks for doing excessive decomposition in a WBS?

Show answerHide answer

Correct answer: D

Non-productive management effort and inefficient use of resources

Question 5 Choose 1

Which statement is true about the project management body of knowledge?

Show answerHide answer

Correct answer: B

Constantly evolving

Question 6 Choose 1

The initial development of a Project Scope Management plan uses which technique?

Show answerHide answer

Correct answer: C

Expert judgment

Question 7 Choose 1

Which of the following is a project constraint?

Show answerHide answer

Correct answer: D

The product is needed in 250 days.

Question 8 Choose 1

An input to the Estimate Activity Resources process is:

Show answerHide answer

Correct answer: C

Resource calendars.

Question 9 Choose 1

The project budget is set at $150,000. The project duration is planned to be one year. At the
completion of Week 16 of the project, the following information is collected: Actual cost = $50,000,
Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

Show answerHide answer

Correct answer: A

0.8

Question 10 Choose 1

Which technique is utilized in the Control Schedule process?

Show answerHide answer

Correct answer: D

Variance analysis

Full mock exam

Sit the CAPM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CAPM mock exam
  • 65questions per mock
  • 105 mintime limit
  • 785questions in the bank
  • Newmock on every attempt