Which tools or techniques will a project manager use for Develop Project Team?
Show answerHide answer
Correct answer: C
Recognition and rewards
Certified Associate in Project Management
Free CAPM mock exam questions 131–140, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Which tools or techniques will a project manager use for Develop Project Team?
Correct answer: C
Recognition and rewards
Which of the following is an input to Direct and Manage Project Execution?
Correct answer: B
Approved change requests
A weighting system is a tool for which area of Conduct Procurements?
Correct answer: C
Selecting seller's
Which type of chart is a graphic representation of a process showing the relationships among
process steps?
Correct answer: C
Flow
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV =
$50,000 AC = $80,000 EV = $40,000
Correct answer: D
0.8
Which tool and technique is used in Conduct Procurements?
Correct answer: C
Bidder conferences
What provides information regarding the ways people, teams, and organizational units behave?
Correct answer: B
Organizational theory
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to
accomplish the project objectives and create the required deliverables?
Correct answer: D
Work breakdown structure (WBS)
What causes replanning of the project scope?
Correct answer: D
Change requests
Which of the following is an output of the Distribute Information process?
Correct answer: C
Organizational process assets updates
Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.