In the Develop Project Team process, which of the following is identified as a critical factor for a
project's success?
Show answerHide answer
Correct answer: D
Teamwork
Certified Associate in Project Management
Free CAPM mock exam questions 141–150, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
In the Develop Project Team process, which of the following is identified as a critical factor for a
project's success?
Correct answer: D
Teamwork
The project scope statement and resource calendars are inputs to which Project Time
Management process?
Correct answer: C
Develop Schedule
Which process determines the risks that might affect the project?
Correct answer: B
Identify Risks
Which of the following is an input to the Direct and Manage Project Execution process?
Correct answer: A
Approved change requests
Which of the following factors is lowest at the start of the project?
Correct answer: A
Cost of changes
In which domain of project management would a Pareto chart provide useful information?
Correct answer: D
Project Quality Management
Ensuring that both parties meet contractual obligations and that their own legal rights are
protected is a function of:
Correct answer: C
Administer Procurements,
In which process might a project manager use risk reassessment as a tool and technique?
Correct answer: B
Monitor and Control Risk
A purchase order for a specified item to be delivered by a specified date for a specified price is the
simplest form of what type of contract?
Correct answer: C
Fixed price or lump-sum
What risk technique is used to quantify the probability and impact of risks on project objectives?
Correct answer: D
Interviewing