PRINCE2 certification · Exam PRINCE2-Practitioner

PRINCE2-Practitioner Mock Exam Page 2

PRINCE2 Practitioner Exam

Free PRINCE2-Practitioner questions on Topic 1: PRINCE2 Principles, each with the answer and an explanation.

20 questions · 33 minutes · free, no sign-up

Topic 1: PRINCE2 Principles questions

11–15 of 15 free
Question 11 Choose 2

Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job
very well. He injured his leg two years ago which has restricted his visits to the engineering
area. As CEO he has an overall perspective of the business strategic requirements and the
authority to commit resources as required.
Marketing Director: She has been with the company for three years, following a
successful career with a publicity company. She has the ability to represent the needs of
the business, particularly as this is a marketing project. She has the authority to commit the
annual business marketing budget, from which the project will be funded, as she sees
appropriate. She will be responsible for monitoring the expected benefits of the calendar, in
particular the improvement of the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the
company and is still as keen and energetic as the day he started. VVhilst he will not be part
of the project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document
control. They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and
office equipment needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent
photographers and a history of successful work. This company has been selected to take
the photos for the company calendar. It has yet be decided which of the photographers to
use.
Which 2 statements explain why the Marketing Director should be appointed as the
Executive for this project?

Show answerHide answer

Correct answer: C, D

She is able to represent the business needs of MNO Manufacturing.

She has authority to commit the marketing budget, from which the project will be funded.

Question 12 Choose 1

Which role is responsible for providing the customer's quality expectations and acceptance
criteria for the project?

Show answerHide answer

Correct answer: C

Senior User

Question 13 Choose 2

Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the
role of Team Manager after taking some time to understand the requirements of the
project. A contract for their services has been set up and is being monitored by the
Purchasing Manager and a Work Package has been agreed. This contract specifies that
the photographer must arrange a meeting with the Engineering Manager to establish a
schedule for the photo sessions to minimize the impact on the Engineering staff. This
meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he
reported that he has received no communication from the photographer. The Project
Manager has tried to call the photographer and has had no response. The Project Manager
believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients'
work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected
benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a
competitor also producing a calendar to be delivered earlier than the target date for this
project. There is a threat that the early release of a competitor's calendar may weaken the
impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated
benefits of the Calendar project.Which 2 statements should be recorded under either the Records or Reporting headings?

Show answerHide answer

Correct answer: B, C

The evaluated net effect of all risks will be updated at the end of each stage and
included in the End Stage Report.

The Change Authority will report monthly to the Project Manager on the status of the
change budget.

Question 14 Choose 1

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which
contains a document control process to manage all documentation requirements.
The document control process was created by the MFH Quality Manager, who now
maintains all of MFH's documents and performs an organization-wide configuration
management role. The MFH Quality Manager will administer the configuration
management procedure for the Restructuring project since this must comply with
the MFH document control process.
According to PRINCE2, which statement about appointing the MFH Quality Manager to
administer the configuration management procedure is correct?

Show answerHide answer

Correct answer: C

The MFH Quality Manager would be suitable to perform this task because he is the
author of the document control process and is likely to have the knowledge required for this
role.

Question 15 Choose 2

Scenario:
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2. Work is to start at the beginning of week 2 (Stage 4).
3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT
equipment.
6. Installation work must take place during MFH normal working hours.
7. +£10,000 / -£25,000.
Reporting arrangements
8. Highlight Report every Monday by 10.00 am.
9. The report must contain a summary of all products worked on during the previous week.
10. Project Manager must be notified of any issues immediately by telephone
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
Which 2 statements apply to either the Reporting arrangements or Problem handling and
escalation sections?

Show answerHide answer

Correct answer: D, E

Add 'Any risks identified to be added to the Risk Register' to Reporting arrangements.

Delete entry 11 because the impact analysis should be provided when the issue is
notified.

That's the last free question in Topic 1: PRINCE2 Principles

You've seen the free 30% (15 of 50 questions). Full access unlocks every question and full-length PRINCE2-Practitioner mock exams (65 questions, 105 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the PRINCE2-Practitioner exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PRINCE2-Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PRINCE2-Practitioner mock exam
  • 65questions per mock
  • 105 mintime limit
  • 274questions in the bank
  • Newmock on every attempt