Which input to the Plan Risk Management process provides information on high-level risks?
Show answerHide answer
Correct answer: A
Project charter
Certified Associate in Project Management
Free CAPM mock exam questions 41–50, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Which input to the Plan Risk Management process provides information on high-level risks?
Correct answer: A
Project charter
Which input may influence quality assurance work and should be monitored within the context of a
system for configuration management?
Correct answer: B
Project documents
Change requests are processed for review and disposition according to which process?
Correct answer: D
Perform Integrated Change Control
The review of a sellers progress toward achieving the goals of scope and quality within cost and
schedule compared to the contract is known as:
Correct answer: D
Procurement performance reviews.
An input to Develop Project Charter is a/an:
Correct answer: A
Business case.
Which item is a formal proposal to modify any document, deliverable, or baseline?
Correct answer: A
Change request
Which risk management strategy seeks to eliminate the uncertainty associated with a particular
upside risk by ensuring that the opportunity is realized?
Correct answer: C
Exploit
The degree, amount, or volume of risk that an organization or individual will withstand is known as
its risk:
Correct answer: C
Tolerance
Project deliverables that have been completed and checked for correctness through the Control
Quality process are known as:
Correct answer: A
Verified deliverables.
An output of the Perform Integrated Change Control process is:
Correct answer: C
The change log.
Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full CAPM mock exam