Free CAPM mock exam questions 11–20, each with the answer and an explanation.

20 questions · 33 minutes · free, no sign-up

Free CAPM questions

11–20 of 232 free
Question 11 Choose 1

Which input to the Manage Stakeholder Engagement process is used to document changes that
occur during the project?

Show answerHide answer

Correct answer: B

Change log

Question 12 Choose 1

An input to the Plan Stakeholder Management process is:

Show answerHide answer

Correct answer: D

A stakeholder register.

Question 13 Choose 1

An input to the Plan Cost Management process is: 

Show answerHide answer

Correct answer: C

 The project charter,

Question 14 Choose 1

A technique used to determine the cause and degree of difference between baseline and actual
performance is:

Show answerHide answer

Correct answer: B

Variance analysis.

Question 15 Choose 1

The process of identifying and documenting project roles, responsibilities, required skills, and
reporting relationships and creating a staffing management plan is known as:

Show answerHide answer

Correct answer: D

Plan Human Resource Management.

Question 16 Choose 1

Which type of dependency is legally or contractually required or inherent in the nature of work and
often involves physical limitations?

Show answerHide answer

Correct answer: A

Mandatory

Question 17 Choose 1

During which process does a project manager review all prior information to ensure that all project
work is completed and that the project has met its objectives?

Show answerHide answer

Correct answer: C

Close Project or Phase

Question 18 Choose 1

An input to the Manage Project Team process is:

Show answerHide answer

Correct answer: A

Work performance reports.

Question 19 Choose 1

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

Show answerHide answer

Correct answer: A

Procurement statement of work

Question 20 Choose 1

A large portion of a projects budget is typically expended on the processes in which Process
Group?

Show answerHide answer

Correct answer: B

Planning

Full mock exam

Sit the CAPM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CAPM mock exam
  • 65questions per mock
  • 105 mintime limit
  • 785questions in the bank
  • Newmock on every attempt