Question 221

Which statement is related to the project manager's sphere of influence at the
organizational level?

Show answerHide answer

Correct answer: A

A project manager interacts with other project managers to detect common interests and
impacts between their projects.

Question 222 Choose 1

When project requirements are documented in user stones then prioritized and refined just
prior to construction, which approach is being used for scheduling?

Show answerHide answer

Correct answer: A

Iterative scheduling with backlog

Question 223 Choose 1

A project stakeholder is requesting changes to the project plan. Which process group
addresses this?

Show answerHide answer

Correct answer: D

Monitoring and Controlling Process Group

Question 224 Choose 1

To which knowledge area does the Collect Requirements process belong?

Show answerHide answer

Correct answer: B

Scope Management

Question 225 Choose 1

Which of the following lists represents the outputs of the Monitor Communications process?

Show answerHide answer

Correct answer: B

Work performance information, change requests, project management plan updates,
and project documents updates

Question 226 Choose 1

Which of the following are outputs from the process of creating a work breakdown structure
(WBS)?

Show answerHide answer

Correct answer: B

Scope baseline and project documents update

Question 227 Choose 1

Which are examples of processes that may be used once or at predefined points in the
project life cycle?

Show answerHide answer

Correct answer: A

Develop Project Charter and Close Project or Phase

Question 228 Choose 1

Which is an example of analogous estimating?

Show answerHide answer

Correct answer: B

Estimates are created by using information about resources of previous similar projects.

Question 229 Choose 1

A sponsor asks a project manager to provide a project's expected total costs based on its
progress. What formula should the project manager use to determine this?

Show answerHide answer

Correct answer: B

Estimate at completion (EAC) - AC

Question 230 Choose 1

Given the following information.
Activity A takes one week.
Activity B takes three weeks.
Activity C takes two weeks.
Activity D takes five weeks.
Activity A starts at the same time as Activity B.
Activity C follows Activity B and Activity A.
Activity D follows Activity C.
How long will it take to complete the project?

Show answerHide answer

Correct answer: D

Ten weeks

Full mock exam

Sit the CAPM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CAPM mock exam
  • 65questions per mock
  • 105 mintime limit
  • 785questions in the bank
  • Newmock on every attempt