Which type of management focuses on ensuring that projects and programs are reviewed to
prioritize resource allocation?
Show answerHide answer
Correct answer: D
Portfolio
Certified Associate in Project Management
Free CAPM mock exam questions 171–180, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Which type of management focuses on ensuring that projects and programs are reviewed to
prioritize resource allocation?
Correct answer: D
Portfolio
Labor, materials, equipment, and supplies are examples of:
Correct answer: C
Resource categories.
One of the tools and techniques of the Manage Project Team process is:
Correct answer: D
conflict management.
The process of monitoring the status of the project to update project progress and manage
changes to the schedule baseline is:
Correct answer: A
Control Schedule.
Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or
content are known as:
Correct answer: A
updates
Which provides the basic framework for managing a project?
Correct answer: A
Project life cycle
A tool and technique used during the Perform Qualitative Risk Analysis process is:
Correct answer: A
risk data quality assessment.
Fast tracking is a schedule compression technique used to shorten the project schedule without
changing project scope. Which of the following can result from fast tracking?
Correct answer: A
The risk of achieving the shortened project time is increased.
Requirements documentation, requirements management plan, and requirements traceability
matrix are all outputs of which process?
Correct answer: B
Collect Requirements
Which of the following is a strategy to deal with positive risks or opportunities?
Correct answer: C
Exploit