The diagram below is an example of a:
Show answerHide answer
Correct answer: A
Risk breakdown structure (RBS).
Certified Associate in Project Management
Free CAPM mock exam questions 201–210, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
The diagram below is an example of a:
Correct answer: A
Risk breakdown structure (RBS).
Who is responsible for initiating a project?
Correct answer: A
Project sponsor
Which type of diagram includes groups of information and shows relationships between factors,
causes, and objectives?
Correct answer: D
Matrix
Activity cost estimates are quantitative assessments of the probable costs required to:
Correct answer: B
Complete project work.
The item that provides more detailed descriptions of the components in the work breakdown
structure (WB5) is called a WBS:
Correct answer: A
dictionary.
How should a stakeholder who is classified as high power and low interest be grouped in a
power/interest grid during stakeholder analysis?
Correct answer: A
Keep satisfied
The project has a current cost performance index of 0.80. Assuming this performance wi continue,
the new estimate at completion is $1000. What was the original budget at completion for the
project?
Correct answer: A
$800
Under which circumstances should multiple projects be grouped in a program?
Correct answer: A
When they are needed to accomplish a set of goals and objectives for an organization
Which action should the project manager take after the team finishes executing the scope?
Correct answer: A
Verify the deliverables to ensure that they are correct and meet the customer's satisfaction.
How can a project manager evaluate project team development?
Correct answer: A
Produce team performance assessments.
Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full CAPM mock exam