Question 201 Choose 1

The diagram below is an example of a:


Show answerHide answer

Correct answer: A

Risk breakdown structure (RBS).

Question 202 Choose 1

Who is responsible for initiating a project?

Show answerHide answer

Correct answer: A

Project sponsor

Question 203 Choose 1

Which type of diagram includes groups of information and shows relationships between factors,
causes, and objectives?

Show answerHide answer

Correct answer: D

Matrix

Question 204 Choose 1

Activity cost estimates are quantitative assessments of the probable costs required to:

Show answerHide answer

Correct answer: B

Complete project work.

Question 205 Choose 1

The item that provides more detailed descriptions of the components in the work breakdown
structure (WB5) is called a WBS:

Show answerHide answer

Correct answer: A

dictionary.

Question 206 Choose 1

How should a stakeholder who is classified as high power and low interest be grouped in a
power/interest grid during stakeholder analysis?

Show answerHide answer

Correct answer: A

Keep satisfied

Question 207 Choose 1

The project has a current cost performance index of 0.80. Assuming this performance wi continue,
the new estimate at completion is $1000. What was the original budget at completion for the
project?

Show answerHide answer

Correct answer: A

$800

Question 208 Choose 1

Under which circumstances should multiple projects be grouped in a program?

Show answerHide answer

Correct answer: A

When they are needed to accomplish a set of goals and objectives for an organization

Question 209 Choose 1

Which action should the project manager take after the team finishes executing the scope?

Show answerHide answer

Correct answer: A

Verify the deliverables to ensure that they are correct and meet the customer's satisfaction.

Question 210 Choose 1

How can a project manager evaluate project team development?

Show answerHide answer

Correct answer: A

Produce team performance assessments.

Full mock exam

Sit the CAPM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CAPM mock exam
  • 65questions per mock
  • 105 mintime limit
  • 785questions in the bank
  • Newmock on every attempt