Which quality control technique illustrates the 80/20 principle?
Show answerHide answer
Correct answer: D
Pareto chart
Certified Associate in Project Management
Free CAPM mock exam questions 191–200, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Which quality control technique illustrates the 80/20 principle?
Correct answer: D
Pareto chart
At the end of the project, what will be the value of SV?
Correct answer: B
Zero
The process of identifying specific actions to be performed to produce project deliverables is:
Correct answer: A
Define Activities.
What is project management?
Correct answer: B
Applying knowledge, skills, tools, and techniques to project activities to meet the project
requirements
Resource calendars are included in the:
Correct answer: A
staffing management plan.
Expected monetary value (EMV) is computed by which equation?
Correct answer: C
Multiplying the value of each possible outcome by the probability of occurrence and adding the
products together
An input to the Collect Requirements process is the:
Correct answer: A
stakeholder register.
Projects are separated into phases or subprojects; these phases include:
Correct answer: A
feasibility study, concept development, design, and prototype.
In which type of contract are the performance targets established at the onset and the final
contract price determined after completion of all work based on the sellers performance?
Correct answer: C
Fixed-Price-Incentive-Fee (FPIF)
Which of the following is an input to the Develop Project Charter process?
Correct answer: C
Business case