Question 71 Choose 1

Which of the following statements about customer's quality expectations and acceptance
criteria are true?
1. Customer's quality expectations form a specific and precise list of measurable criteria
that a project product should meet in order to be acceptable to key stakeholders.
2. Acceptance criteria are often expressed in broad terms as a means to gain common
understanding of general quality requirements.

Show answerHide answer

Correct answer: D

Neither 1 or 2 are true

Question 72 Choose 1

From whom does a Team Manager obtain approval for a completed product?

Show answerHide answer

Correct answer: C

The authoritydefined in the Product Description

Question 73 Choose 1

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ]
with a Team Manager.

Show answerHide answer

Correct answer: C

Work Package cost tolerance

Question 74 Choose 1

Which plan provides the Business Case with costs during the Initiating a Project process?

Show answerHide answer

Correct answer: B

Project Plan

Question 75 Choose 1

Which is NOT represented by one of the three primary categories of stakeholder identified
in PRINCE2?

Show answerHide answer

Correct answer: B

Those who will manage the project on a day-to-day basis

Question 76 Choose 1

Which process is triggered towards the end of the final stage when all the assigned work
has been completed?

Show answerHide answer

Correct answer: C

Closing a Project

Question 77 Choose 1

Which role is responsible for creating Checkpoint Reports?

Show answerHide answer

Correct answer: B

Team Manager

Question 78 Choose 1

Identify the missing words in the following sentence. The role of [ ? ] is responsible for
carrying out a risk response action to respond to a particular risk.

Show answerHide answer

Correct answer: C

the risk actionee

Question 79 Choose 1

What plan is created, and submitted for approval, during the Managing a Stage Boundary
process?

Show answerHide answer

Correct answer: B

Stage Plan

Question 80 Choose 1

Which of the following can be done to control the size of the Project Board on a project that
involves multiple users and suppliers?

Show answerHide answer

Correct answer: C

Create user and supplier groups

Full mock exam

Sit the Prince2-Foundation exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real Prince2-Foundation exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full Prince2-Foundation mock exam
  • 65questions per mock
  • 105 mintime limit
  • 276questions in the bank
  • Newmock on every attempt