Free Prince2-Foundation questions on Topic 1: Volume A, each with the answer and an explanation.

20 questions · 33 minutes · free, no sign-up

Topic 1: Volume A questions

1–10 of 29 free
Question 1 Choose 1

Which statement is FALSE?

Show answerHide answer

Correct answer: C

A project benefit is only realized after the project has closed

Question 2 Choose 1

Why is the Initiating a Project process used?

Show answerHide answer

Correct answer: B

To fully understand how the project objectives will be achieved before committing
significant resources

Question 3 Choose 1

Which statement about the Directing a Project process is FALSE?

Show answerHide answer

Correct answer: C

Covers the day-to-day activities of the Project Manager

Question 4 Choose 1

Which risk response type is appropriate to respond to an opportunity?

Show answerHide answer

Correct answer: C

Exploit

Question 5 Choose 1

Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work
Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in
the original Project Initiation Documentation have been achieved. Packages for the work
performed in the final stage.

Show answerHide answer

Correct answer: B

Only 2 is true

Question 6 Choose 1

Which should be funded by a change budget?

Show answerHide answer

Correct answer: A

Increase in agreed scope

Question 7 Choose 1

Which is a task of product-based planning?

Show answerHide answer

Correct answer: B

Create the product flow diagram

Question 8 Choose 1

Which is the purpose of the Change theme?

Show answerHide answer

Correct answer: B

Identify, assess and control any potential and approved changes to baselined products

Question 9 Choose 1

Which regular report provides the Project Board with a summary of stage status?

Show answerHide answer

Correct answer: C

Highlight Report

Question 10 Choose 1

Which is part of the PRINCE2 definition of a project?

Show answerHide answer

Correct answer: D

A temporary organization that is created for the purpose of deliveringbusiness products

Full mock exam

Sit the Prince2-Foundation exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real Prince2-Foundation exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.