Question 21 Choose 1

If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated
to for a decision?

Show answerHide answer

Correct answer: C

Corporate/programme management

Question 22 Choose 1

Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits
laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should
be referred to the Project Manager down by the Project Board.

Show answerHide answer

Correct answer: C

Both 1 and 2 are true

Question 23 Choose 1

Which is a benefit of using PRINCE2?

Show answerHide answer

Correct answer: B

Provides for the efficient and economic use of management time

Question 24 Choose 1

When considering risks, which describes an opportunity in a project?

Show answerHide answer

Correct answer: B

An uncertain event that could have a favourable impact on objectives

Explanation

Which of the following is the Business Case used for during the Managing a Stage
Boundary process?

Question 25 Choose 1

Which is NOT a type of issue?

Show answerHide answer

Correct answer: B

A constraint

Question 26 Choose 1

Which is a responsibility of a risk owner?

Show answerHide answer

Correct answer: C

Manage, monitor and control all aspects of an assigned risk

Question 27 Choose 1

Which product summarizes progress and is used to decide whether to amend the project
scope or stop the project?

Show answerHide answer

Correct answer: B

End Stage Report

Question 28 Choose 1

Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels
of [?] to reflect the needs of the different levels of management involved in a project,

Show answerHide answer

Correct answer: B

Plan

Question 29 Choose 1

Which is an objective of the quality review technique?

Show answerHide answer

Correct answer: A

To baseline a product

Question 30 Choose 1

If Work Package tolerance is forecast to be exceeded, to whom should the Team Manager
report?

Show answerHide answer

Correct answer: D

Project Manager

Full mock exam

Sit the Prince2-Foundation exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real Prince2-Foundation exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full Prince2-Foundation mock exam
  • 65questions per mock
  • 105 mintime limit
  • 276questions in the bank
  • Newmock on every attempt