Which statement about risks is FALSE?
Show answerHide answer
Correct answer: C
A risk that a project's product is incomplete is known as an off-specification
PRINCE2 Foundation Exam
Free Prince2-Foundation mock exam questions 31–40, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Which statement about risks is FALSE?
Correct answer: C
A risk that a project's product is incomplete is known as an off-specification
Which should be funded from a change budget?
Correct answer: C
An agreed change to the scope of a project
Which is a purpose of the Directing a Project process?
Correct answer: B
Enable overall control of a project to be exercised by the Project Board
Which statement is true for ALL project stakeholders?
Correct answer: B
May either affect or be affected by the project
Which PRINCE2 principle helps to address a concern that the project team may NOT have
worked on a similar project?
Correct answer: B
Learn from experience
What is the collective name for individuals or groups who may be affected by a project?
Correct answer: C
Stakeholders
Which enables the project's products and all interdependencies to be clearly identified and
documented?
Correct answer: C
Product-based planning technique
Which is a responsibility of a Team Manager?
Correct answer: D
Ensuring delivery of products in the Managing Product Delivery process
In what product should the quality criteria for a specialist product be recorded?
Correct answer: C
Product Description
Which product describes the roles and responsibilities for achieving the effective
management of anticipated threats and opportunities in a project?
Correct answer: B
Risk Management Strategy