Question 1 Choose 1

What product records any time tolerances agreed between the Project Manager and Team
Manager?

Show answerHide answer

Correct answer: B

Work Package

Question 2 Choose 1

Which is NOT obtained from a product's Product Description?

Show answerHide answer

Correct answer: D

The development method to be used

Question 3 Choose 1

Which is an objective of the Initiating a Project process?

Show answerHide answer

Correct answer: C

Summarize how the organization's project management method will be tailored for the
project

Question 4 Choose 1

What needs to be in place to ensure effective issue and change control?

Show answerHide answer

Correct answer: A

Configuration management system

Question 5 Choose 1

Which role is part of the Project Board?

Show answerHide answer

Correct answer: D

Senior Supplier

Question 6 Choose 1

Which does the Executive need to ensure is in place before the project is initiated?

Show answerHide answer

Correct answer: B

An understanding of how the project will contribute to corporate objectives

Question 7 Choose 1

Which of the following are typical core activities within configuration management?
1. Planning
2. Risk assessment
3. Verification and audit
4. Identification

Show answerHide answer

Correct answer: C

1, 3 ,4

Question 8 Choose 1

Which project characteristic suggests that projects should have a defined start and a
defined end?

Show answerHide answer

Correct answer: B

Temporary

Question 9 Choose 1

Identify the missing words in the following sentence.
At the end of a stage, the [ ? ] should be used to check whether there is a requirement to
send copies of the End Stage Report to external interested parties.

Show answerHide answer

Correct answer: B

Communication Management Strategy

Question 10 Choose 1

Identify the missing words in the following sentence.
Configuration management typically includes [ ? ] as one of the five core activities.

Show answerHide answer

Correct answer: D

status accounting

Full mock exam

Sit the Prince2-Foundation exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real Prince2-Foundation exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full Prince2-Foundation mock exam
  • 65questions per mock
  • 105 mintime limit
  • 276questions in the bank
  • Newmock on every attempt