Which activity takes place within the Managing a Stage Boundary process?
Show answerHide answer
Correct answer: C
Produce an Exception Plan
PRINCE2 Foundation Exam
Free Prince2-Foundation mock exam questions 51–60, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Which activity takes place within the Managing a Stage Boundary process?
Correct answer: C
Produce an Exception Plan
Which is an objective of the Directing a Project process?
Correct answer: B
Ensure corporate or programme management has an interface to the project
What do acceptance criteria identify?
Correct answer: C
The measureable definitions of the attributes for a set of products to be acceptable to key stakeholders
Which is a purpose of a Configuration Management Strategy?
Correct answer: B
Define how theproducts and their versions will be identified
Which is one of the three levels of plan in PRINCE2?
Correct answer: C
Team Plan
Which is a purpose of an End Stage Report?
Correct answer: A
Summarize progress to enable the Project Board to decide what action to take next
What product records any time tolerances agreed between the Project Manager and Team
Manager?
Correct answer: B
Work Package
Which is NOT obtained from a product's Product Description?
Correct answer: D
The development method to be used
Which is an objective of the Initiating a Project process?
Correct answer: C
Summarize how the organization's project management method will be tailored for the
project
What needs to be in place to ensure effective issue and change control?
Correct answer: A
Configuration management system