In which strategy would the change control process be recorded?
Show answerHide answer
Correct answer: B
Configuration Management Strategy
PRINCE2 Practitioner Exam
Free PRINCE2 Practitioner mock exam questions 31–40, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
In which strategy would the change control process be recorded?
Correct answer: B
Configuration Management Strategy
If the Project Board are too busy to authorize all change requests themselves they can appoint?
Correct answer: C
A Change Committee
What is the purpose of a Product Status Account?
Correct answer: D
A report covering the status about the state of the projects products within
If Project tolerances were threatened, who needs to be notified?
Correct answer: C
Corporate or Programme Management
During which process would the stage tolerances be set?
Correct answer: D
Directing a Project
Which of the following is not a factor to consider when determining the length of a stage?
Correct answer: A
The amount of resources available h the short term
Which statement is TRUE with regard to technical stages?
Correct answer: C
Technical stages often overlap
There are two time driven controls in PRINCE2, which are they?
Correct answer: B
Highlight and Checkpoint Reports
Starting Up a project is triggered by which of the following?
Correct answer: D
Mandate
Who is responsible for appointing the Project Manager?
Correct answer: C
The Executive