Question 1 Choose 1

Starting Up a project is triggered by which of the following?

Show answerHide answer

Correct answer: D

 Mandate

Question 2 Choose 1

Who is responsible for appointing the Project Manager?

Show answerHide answer

Correct answer: C

The Executive

Question 3 Choose 1

During which of the following activities is the Project Product Description created?

Show answerHide answer

Correct answer: B

Prepare the outline business case

Question 4 Choose 1

Which of the following is NOT an objective of Initiating a Project?

Show answerHide answer

Correct answer: B

Understanding the roles and responsibilities of the Project Management Team

Question 5 Choose 1

Which other management product is created when the Business case is updated during Initiating a
Project?

Show answerHide answer

Correct answer: C

Benefits Review plan

Question 6 Choose 1

Who is responsible for the initial creation of the Configuration Item records?

Show answerHide answer

Correct answer: D

Project Support

Question 7 Choose 1

Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues. lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
There is no project schedule in the Project Initiation Documentation. How can project progress be
tracked without a schedule to track against?

Show answerHide answer

Correct answer: B

Progress can be recorded and tracked using the product checklist, with the planned and actual
quality management activities captured in the Daily Log.

Question 8 Choose 1

Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues. lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
There is no Project Brief. How can there be a common understanding of the desired outcomes for
the prepared calendar pack?

Show answerHide answer

Correct answer: C

The simple Project Initiation Documentation contains the project definition.

That's the last free question in Topic 9, Starting up and Initiating a Project

You've seen the free 30% (8 of 29 questions). Full access unlocks every question and full-length PRINCE2 Practitioner mock exams (65 questions, 105 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the PRINCE2 Practitioner exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PRINCE2 Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PRINCE2 Practitioner mock exam
  • 65questions per mock
  • 105 mintime limit
  • 189questions in the bank
  • Newmock on every attempt