Starting Up a project is triggered by which of the following?
Show answerHide answer
Correct answer: D
Mandate
PRINCE2 Practitioner Exam
Free PRINCE2 Practitioner questions on Topic 9, Starting up and Initiating a Project, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Starting Up a project is triggered by which of the following?
Correct answer: D
Mandate
Who is responsible for appointing the Project Manager?
Correct answer: C
The Executive
During which of the following activities is the Project Product Description created?
Correct answer: B
Prepare the outline business case
Which of the following is NOT an objective of Initiating a Project?
Correct answer: B
Understanding the roles and responsibilities of the Project Management Team
Which other management product is created when the Business case is updated during Initiating a
Project?
Correct answer: C
Benefits Review plan
Who is responsible for the initial creation of the Configuration Item records?
Correct answer: D
Project Support
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues. lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
There is no project schedule in the Project Initiation Documentation. How can project progress be
tracked without a schedule to track against?
Correct answer: B
Progress can be recorded and tracked using the product checklist, with the planned and actual
quality management activities captured in the Daily Log.
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues. lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
There is no Project Brief. How can there be a common understanding of the desired outcomes for
the prepared calendar pack?
Correct answer: C
The simple Project Initiation Documentation contains the project definition.
You've seen the free 30% (8 of 29 questions). Full access unlocks every question and full-length PRINCE2 Practitioner mock exams (65 questions, 105 minutes), a different mock on every attempt.
Full-length mocks with the same number of questions and the same time limit as the real PRINCE2 Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full PRINCE2 Practitioner mock exam