Which of the following is the definition for an off-specification?
Show answerHide answer
Correct answer: B
Something forecast or currently not meeting specification
PRINCE2 Practitioner Exam
Free PRINCE2 Practitioner questions on Topic 7, Change Theme, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Which of the following is the definition for an off-specification?
Correct answer: B
Something forecast or currently not meeting specification
In which strategy would the change control process be recorded?
Correct answer: B
Configuration Management Strategy
If the Project Board are too busy to authorize all change requests themselves they can appoint?
Correct answer: C
A Change Committee
What is the purpose of a Product Status Account?
Correct answer: D
A report covering the status about the state of the projects products within
You've seen the free 30% (4 of 14 questions). Full access unlocks every question and full-length PRINCE2 Practitioner mock exams (65 questions, 105 minutes), a different mock on every attempt.
Full-length mocks with the same number of questions and the same time limit as the real PRINCE2 Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full PRINCE2 Practitioner mock exam