When does Directing a Project begin?
Show answerHide answer
Correct answer: C
From the completion of Starting up a Project
PRINCE2 Practitioner Exam
Free PRINCE2 Practitioner questions on Topic 10, Directing a Project, Controlling a Stage and Managing Product Delivery, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
When does Directing a Project begin?
Correct answer: C
From the completion of Starting up a Project
Which management product do the Project Board use to decide whether to authorize initiation?
Correct answer: A
Project Brief
Which of the following is NOT a trigger for the project manager to authorize a work package?
Correct answer: D
Reporting highlights
You've seen the free 30% (3 of 11 questions). Full access unlocks every question and full-length PRINCE2 Practitioner mock exams (65 questions, 105 minutes), a different mock on every attempt.
Full-length mocks with the same number of questions and the same time limit as the real PRINCE2 Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full PRINCE2 Practitioner mock exam