When updating the project plan as part of Managing a stage boundary, what else might be
updated?
Show answerHide answer
Correct answer: A
Exception Plan
PRINCE2 Practitioner Exam
Free PRINCE2 Practitioner questions on Topic 11, Managing a Stage Boundary and Closing a Project, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
When updating the project plan as part of Managing a stage boundary, what else might be
updated?
Correct answer: A
Exception Plan
Which of the following management products ARE updated as part of Managing a stage
boundary?
1. Business Case
2. Benefits Review Plan
3. Configuration Item Records
4. Project Brief
Correct answer: A
1, 2, 3
Which of the following activities could trigger the production of an exception plan?
Correct answer: B
Giving ad hoc direction
You've seen the free 30% (3 of 13 questions). Full access unlocks every question and full-length PRINCE2 Practitioner mock exams (65 questions, 105 minutes), a different mock on every attempt.
Full-length mocks with the same number of questions and the same time limit as the real PRINCE2 Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full PRINCE2 Practitioner mock exam