Which of the following is False?
A Successful project management team should.
Show answerHide answer
Correct answer: B
Never be reviewed as members should stay with the team for the duration
PRINCE2 Practitioner Exam
Free PRINCE2 Practitioner questions on Topic 3, Organization Theme, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Which of the following is False?
A Successful project management team should.
Correct answer: B
Never be reviewed as members should stay with the team for the duration
Which of the following statements is true of the business interest on the project?
Correct answer: A
Ensures the project provides value for money
Which of the following represents the four key characteristics a good Project board should
display?
Correct answer: B
Authority, Credibility, Delegation, Availability
In which Management product would the Project Board specify where the authority for change
requests lies?
Correct answer: D
Configuration Management Strategy
Who is responsible for ensuring that Communication Management Strategy is appropriate and that
planned communication activities actually take place?
Correct answer: A
Project Assurance
Which of the following roles cannot be combined?
Correct answer: C
Project Assurance and Team Manager
You've seen the free 30% (6 of 21 questions). Full access unlocks every question and full-length PRINCE2 Practitioner mock exams (65 questions, 105 minutes), a different mock on every attempt.
Full-length mocks with the same number of questions and the same time limit as the real PRINCE2 Practitioner exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full PRINCE2 Practitioner mock exam