Which type of estimate refers to estimating a story based on its relationship to one or more
other stories?
Show answerHide answer
Correct answer: A
Algorithmic
PMI Agile Certified Practitioner
Free PMI-ACP mock exam questions 61–62, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Which type of estimate refers to estimating a story based on its relationship to one or more
other stories?
Correct answer: A
Algorithmic
An organization adopts Agile practices and implements an incremental delivery strategy. If
implemented correctly, the company should recognize improved:
Correct answer: D
project Return on Investment (ROI) by releasing individual features to market.
You've seen the free 30% (62 of 208 questions). Full access unlocks every question and full-length PMI-ACP mock exams (65 questions, 105 minutes), a different mock on every attempt.
Full-length mocks with the same number of questions and the same time limit as the real PMI-ACP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full PMI-ACP mock exam