What is used to provide a simple medium for gathering basic information about stories,
recording high-level requirements, developing work estimates, and defining acceptance
tests?
Show answerHide answer
Correct answer: A
Story card
PMI Agile Certified Practitioner
Free PMI-ACP mock exam questions 21–30, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
What is used to provide a simple medium for gathering basic information about stories,
recording high-level requirements, developing work estimates, and defining acceptance
tests?
Correct answer: A
Story card
Which answer best describes Wide Band Delphi (e. g. Planning Poker) estimating?
Correct answer: A
Team members provide story estimates individually and discuss their reasoning until a consensus on the estimate is reached.
User stories are temporary artifacts. They are considered relevant until the:
Correct answer: A
Team completes them.
For a critical project, a new team has been formed from various departments. The project
manager should start team building by:
Correct answer: C
Assembling the team and discussing roles and responsibilities of each member on the
team.
The most appropriate model for a geographically distributed project team is one in which
the team is distributed across:
Correct answer: A
relatively few locations, with each location team comprised of a complete development
group developing decoupled subsystems.
In a Lean project environment, visual controls:
Correct answer: A
Can be used by management for communicating specific corrective direction.
Which of the following is an example of a visual aid used in Lean-Agile software
development?
Correct answer: A
Business value delivered chart
What is one of the main benefits that Lean portfolio management provides to a business?
Correct answer: C
Line of sight to business needs
On a project using eXtreme Programming (XP), a customer test is a:
Correct answer: B
Tool for a customer to verify the business requirements.
During which activity is the sequence of numbers 0, 1, 2, 3, 5, 8, 13 often used?
Correct answer: C
Indicating priority of a story