Question 21 Choose 1

What is used to provide a simple medium for gathering basic information about stories,
recording high-level requirements, developing work estimates, and defining acceptance
tests?

Show answerHide answer

Correct answer: A

Story card

Question 22 Choose 1

Which answer best describes Wide Band Delphi (e. g. Planning Poker) estimating?

Show answerHide answer

Correct answer: A

Team members provide story estimates individually and discuss their reasoning until a consensus on the estimate is reached.

Question 23 Choose 1

User stories are temporary artifacts. They are considered relevant until the:

Show answerHide answer

Correct answer: A

Team completes them.

Question 24 Choose 1

For a critical project, a new team has been formed from various departments. The project
manager should start team building by:

Show answerHide answer

Correct answer: C

Assembling the team and discussing roles and responsibilities of each member on the
team.

Question 25 Choose 1

The most appropriate model for a geographically distributed project team is one in which
the team is distributed across:

Show answerHide answer

Correct answer: A

relatively few locations, with each location team comprised of a complete development
group developing decoupled subsystems.

Question 26 Choose 1

In a Lean project environment, visual controls:

Show answerHide answer

Correct answer: A

Can be used by management for communicating specific corrective direction.

Question 27 Choose 1

Which of the following is an example of a visual aid used in Lean-Agile software
development?

Show answerHide answer

Correct answer: A

Business value delivered chart

Question 28 Choose 1

What is one of the main benefits that Lean portfolio management provides to a business?

Show answerHide answer

Correct answer: C

Line of sight to business needs

Question 29 Choose 1

On a project using eXtreme Programming (XP), a customer test is a:

Show answerHide answer

Correct answer: B

Tool for a customer to verify the business requirements.

Question 30 Choose 1

During which activity is the sequence of numbers 0, 1, 2, 3, 5, 8, 13 often used?

Show answerHide answer

Correct answer: C

Indicating priority of a story

Full mock exam

Sit the PMI-ACP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMI-ACP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMI-ACP mock exam
  • 65questions per mock
  • 105 mintime limit
  • 208questions in the bank
  • Newmock on every attempt