In Agile projects, how are planning outputs shared with stakeholders?
Show answerHide answer
Correct answer: A
Using the most highly visible method possible
PMI Agile Certified Practitioner
Free PMI-ACP mock exam questions 41–50, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
In Agile projects, how are planning outputs shared with stakeholders?
Correct answer: A
Using the most highly visible method possible
When developing user stories, user expectations are best captured in what form?
Correct answer: A
Acceptance tests
Which term best describes an Agile project's approach to risk analysis?
Correct answer: D
Monte Carlo
When facilitated and managed well, the primary benefits of a project retrospective should
be to:
Correct answer: D
Allow the team to get ahead on release planning.
What is the first thing that a team should do to estimate user stories for a project?
Correct answer: C
Define the story points measure.
Risk exposure is the:
Correct answer: A
Funds set aside to contain the risk.
In Agile risk management, a risk burndown chart is best used to:
Correct answer: D
Illustrate the project risk profile and new and changing risks.
What are the primary outputs of a release planning session?
Correct answer: D
Risks, action items, dependencies, and Release Backlog
A user story says that a product must be very fast. During the demo, the Product Owner is
dissatisfied with the speed of the product. The most likely reason that this occurred is
because the user story was:
Correct answer: C
Not testable.
What is a high-level representation of the features or themes that are to be delivered in
each release?
Correct answer: B
Product roadmap
Full-length mocks with the same number of questions and the same time limit as the real PMI-ACP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full PMI-ACP mock exam