When is the ideal time to hold a retrospective?
Show answerHide answer
Correct answer: B
Just before iteration planning
PMI Agile Certified Practitioner
Find out if you're ready for PMI-ACP. Take the free timed mock exam and get your score in minutes, or study the free PMI-ACP questions below with answers and explanations.
20 questions · 33 minutes · free, no sign-up
When is the ideal time to hold a retrospective?
Correct answer: B
Just before iteration planning
An Agile team best ensures product quality through:
Correct answer: C
More frequent inspection after each iteration
A technique showing Kanban work stages by comparing counted features over a time
interval is called a/an:
Correct answer: C
Cumulative flow diagram.
The key elements of a user story in Agile development are:
Correct answer: B
conversations about the story, a written description, and success criteria about the story.
The team estimation game method mainly consists of a:
Correct answer: A
Pile of cards with user, capability, and value to be prioritized by the project team.
How is the participatory design process characterized?
Correct answer: C
End users participate and assist in the design process from the beginning of the project.
When moving to Agile project management, a key factor for the project manager’s success
will be:
Correct answer: A
shifting from a controlling mindset to a facilitating mindset
The best reason for extreme character personas in writing user stories is to:
Correct answer: B
Help identify user stories that would otherwise be missed.
When estimating initial velocity, the team should most likely:
Correct answer: C
Use velocity of past iterations or make a calculated guess.
Who is responsible for determining the business value of each feature?
Correct answer: A
Product Owner
Full-length mocks with the same number of questions and the same time limit as the real PMI-ACP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full PMI-ACP mock exam